ICT-Governance-Framework-Application

Communication Schedule

ICT Governance Framework Implementation Project

Document Control Information

Document Information  
Document Title Communication Schedule
Project ICT Governance Framework
Version 1.0
Date August 11, 2025
Author Project Manager
Reviewer Communications Lead
Approver Project Sponsor
WBS Code 1.1.2.1.4
Activity ID A012
Status Baselined

Executive Summary

This Communication Schedule provides a detailed timeline and framework for all project communications throughout the ICT Governance Framework implementation. It defines specific communication events, frequencies, responsibilities, and deliverables to ensure consistent and effective stakeholder engagement.

Key Features:


Communication Schedule Overview

Schedule Principles

  1. Stakeholder-Centric: All communications designed around stakeholder needs and preferences
  2. Frequency Optimization: Balanced frequency to maintain engagement without overwhelming
  3. Escalation Pathways: Clear escalation routes for urgent communications
  4. Feedback Integration: Regular feedback collection and schedule adjustments
  5. Quality Assurance: Review and approval processes for all formal communications

Communication Phases

Phase Duration Focus Key Communications
Initiation Weeks 1-4 Project launch and stakeholder alignment Kickoff, charter approval, initial briefings
Planning Weeks 5-12 Detailed planning and stakeholder buy-in Planning reviews, requirement validation, resource confirmation
Execution Weeks 13-40 Implementation and progress tracking Status reports, milestone updates, issue resolution
Monitoring Weeks 13-44 Continuous oversight and adjustment Performance dashboards, risk reviews, change communications
Closure Weeks 41-44 Project completion and transition Final reports, lessons learned, handover communications

Detailed Communication Schedule

Phase 1: Initiation (Weeks 1-4)

Week 1

| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Project Kickoff Meeting | All Stakeholders | Project Manager | In-person/Virtual | 2 hours | | Wed | Executive Sponsor Briefing | Executive Sponsors | Project Manager | Presentation | 1 hour | | Fri | Team Formation Meeting | Core Project Team | Project Manager | In-person | 1.5 hours |

Week 2

| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Stakeholder Registration Confirmation | All Stakeholders | Communications Lead | Email | N/A | | Wed | Steering Committee Formation | Steering Committee | Project Sponsor | Meeting | 1 hour | | Fri | Department Manager Briefings | Department Managers | Change Manager | Presentation | 45 min each |

Week 3

| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Technical Team Orientation | Technical Team | Technical Lead | Workshop | 3 hours | | Wed | First Steering Committee Meeting | Steering Committee | Project Manager | Meeting | 2 hours | | Fri | Stakeholder Feedback Session | Key Stakeholders | Communications Lead | Survey/Interviews | Ongoing |

Week 4

| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Project Charter Review | Executive Sponsors | Project Manager | Document Review | N/A | | Wed | Communication Plan Approval | Steering Committee | Communications Lead | Presentation | 30 min | | Fri | Phase 1 Completion Report | All Stakeholders | Project Manager | Email/Portal | N/A |

Phase 2: Planning (Weeks 5-12)

Weekly Recurring Communications

| Communication Item | Frequency | Day | Time | Audience | Owner | Format | |——————-|———–|—–|——|———-|——-|——–| | Project Status Meeting | Weekly | Monday | 9:00 AM | Core Team | Project Manager | Virtual Meeting | | Technical Working Group | Weekly | Wednesday | 2:00 PM | Technical Team | Technical Lead | Virtual Meeting | | Stakeholder Check-ins | Bi-weekly | Friday | Various | Key Stakeholders | Communications Lead | Phone/Email |

Monthly Communications

| Communication Item | Week | Audience | Owner | Format | |——————-|——|———-|——-|——–| | Steering Committee Meeting | Week 1 | Steering Committee | Project Manager | Meeting | | Executive Dashboard Update | Week 2 | Executive Sponsors | Project Manager | Dashboard | | Department Manager Briefing | Week 3 | Department Managers | Change Manager | Presentation | | All-Hands Project Update | Week 4 | All Stakeholders | Project Manager | Email/Intranet |

Phase 3: Execution (Weeks 13-40)

Daily Communications

| Communication Item | Frequency | Time | Audience | Owner | Format | |——————-|———–|——|———-|——-|——–| | Team Stand-up | Daily | 8:30 AM | Core Team | Scrum Master | Virtual Meeting | | Issue Escalation (as needed) | As needed | Immediate | Relevant Stakeholders | Issue Owner | Phone/Email |

Weekly Communications

| Communication Item | Day | Time | Audience | Owner | Format | |——————-|—–|——|———-|——-|——–| | Project Status Report | Friday | 5:00 PM | All Stakeholders | Project Manager | Email/Portal | | Risk Review Meeting | Thursday | 10:00 AM | Risk Committee | Risk Manager | Virtual Meeting | | Technical Progress Review | Tuesday | 3:00 PM | Technical Team | Technical Lead | Virtual Meeting |

Bi-weekly Communications

| Communication Item | Week | Audience | Owner | Format | |——————-|——|———-|——-|——–| | Executive Briefing | Odd weeks | Executive Sponsors | Project Manager | Presentation | | Change Impact Assessment | Even weeks | Affected Departments | Change Manager | Report |

Monthly Communications

| Communication Item | Week | Audience | Owner | Format | |——————-|——|———-|——-|——–| | Steering Committee Meeting | Week 1 | Steering Committee | Project Manager | Meeting | | Milestone Review | Week 2 | Key Stakeholders | Project Manager | Presentation | | Training Updates | Week 3 | End Users | Training Lead | Email/Intranet | | Vendor Coordination | Week 4 | External Vendors | Procurement Lead | Meeting |

Phase 4: Monitoring (Weeks 13-44)

Continuous Monitoring Communications

| Communication Item | Frequency | Audience | Owner | Format | |——————-|———–|———-|——-|——–| | Performance Dashboard | Real-time | All Stakeholders | System Administrator | Online Dashboard | | Automated Alerts | As triggered | Relevant Stakeholders | Monitoring System | Email/SMS | | Health Check Reports | Weekly | Technical Team | Operations Lead | Report |

Phase 5: Closure (Weeks 41-44)

Week 41

| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Project Closure Initiation | Core Team | Project Manager | Meeting | | Wed | Final Deliverable Review | Steering Committee | Project Manager | Presentation | | Fri | Transition Planning Meeting | Operations Team | Operations Lead | Meeting |

Week 42

| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Lessons Learned Session | Project Team | Project Manager | Workshop | | Wed | Final Executive Briefing | Executive Sponsors | Project Manager | Presentation | | Fri | Knowledge Transfer Sessions | Support Teams | Technical Lead | Training |

Week 43

| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Project Closure Report | All Stakeholders | Project Manager | Document | | Wed | Final Steering Committee | Steering Committee | Project Manager | Meeting | | Fri | Celebration Event | All Stakeholders | Project Manager | Event |

Week 44

| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Final Documentation Handover | Operations Team | Documentation Lead | Meeting | | Wed | Project Archive Completion | PMO | Project Manager | Process | | Fri | Post-Project Review | Steering Committee | Project Sponsor | Meeting |


Roles and Responsibilities (R&Rs)

Communication Roles

Project Manager

Primary Responsibilities:

Communication Deliverables:

Authority Level: Full authority for routine communications; requires sponsor approval for external communications

Communications Lead

Primary Responsibilities:

Communication Deliverables:

Authority Level: Authority for communication process and quality; escalates content decisions to Project Manager

Technical Lead

Primary Responsibilities:

Communication Deliverables:

Authority Level: Full authority for technical communications; coordinates with Project Manager for business impact

Change Manager

Primary Responsibilities:

Communication Deliverables:

Authority Level: Authority for change-related communications; coordinates with Project Manager for timing

Risk Manager

Primary Responsibilities:

Communication Deliverables:

Authority Level: Authority for risk communications; escalates critical risks to Project Manager

Approval Matrix

Communication Type Preparer Reviewer Approver Timeline
Executive Communications Project Manager Communications Lead Project Sponsor 3 business days
External Communications Communications Lead Project Manager Project Sponsor 5 business days
Technical Documentation Technical Lead Subject Matter Expert Technical Lead 2 business days
Status Reports Project Manager Communications Lead Project Manager 1 business day
Change Communications Change Manager Project Manager Change Manager 2 business days
Risk Communications Risk Manager Project Manager Risk Manager 1 business day
Training Materials Training Lead Subject Matter Expert Training Lead 3 business days
Meeting Minutes Meeting Scribe Meeting Chair Meeting Chair 1 business day

Escalation Procedures

Level 1: Team Level

Level 2: Project Level

Level 3: Executive Level

Level 4: Crisis Level


Communication Quality Assurance

Quality Standards

Content Quality

Format Standards

Review Process

Pre-Distribution Review

  1. Content Review: Subject matter expert validation
  2. Quality Check: Communications lead review
  3. Approval Process: Appropriate authority approval
  4. Final Check: Distribution list and format verification
  5. Distribution: Controlled release to stakeholders

Post-Distribution Follow-up

  1. Delivery Confirmation: Verify receipt by key stakeholders
  2. Feedback Collection: Gather stakeholder responses
  3. Effectiveness Assessment: Measure communication impact
  4. Improvement Identification: Document lessons learned
  5. Process Refinement: Update procedures as needed

Communication Metrics and KPIs

Engagement Metrics

Metric Target Measurement Method Frequency
Stakeholder Response Rate >85% Email responses, meeting attendance Weekly
Communication Satisfaction >4.0/5.0 Stakeholder surveys Monthly
Information Accuracy >95% Feedback analysis, error tracking Monthly
Timeliness Compliance >90% Schedule adherence tracking Weekly
Stakeholder Engagement Score >4.2/5.0 Engagement assessment surveys Quarterly

Effectiveness Metrics

Metric Target Measurement Method Frequency
Decision Speed <3 days average Decision tracking system Monthly
Issue Resolution Time <5 days average Issue management system Weekly
Change Request Processing <7 days average Change management system Monthly
Stakeholder Alignment >80% agreement Alignment surveys Quarterly
Communication ROI Positive trend Cost-benefit analysis Quarterly

Reporting Dashboard

Real-time Metrics

Weekly Reports

Monthly Analysis


Risk Management and Contingency Planning

Communication Risks

Risk Probability Impact Mitigation Strategy Contingency Plan
Stakeholder Disengagement Medium High Regular check-ins, personalized approach Escalation to sponsor, direct intervention
Information Overload High Medium Targeted communications, summary formats Simplified communications, key message focus
Technical Communication Gaps Medium High Technical liaison roles, translation support Expert briefings, simplified documentation
Geographic/Time Zone Challenges High Medium Multiple time slots, recorded sessions Asynchronous communication, regional coordinators
Communication System Failures Low High Backup systems, multiple channels Manual processes, alternative platforms

Contingency Procedures

System Failure Response

  1. Immediate: Switch to backup communication channels
  2. Short-term: Implement manual processes
  3. Medium-term: Restore primary systems
  4. Long-term: Review and improve system resilience

Stakeholder Crisis Response

  1. Assessment: Evaluate stakeholder concerns and impact
  2. Response: Develop targeted response strategy
  3. Communication: Implement crisis communication plan
  4. Recovery: Rebuild stakeholder confidence and engagement

Change Control and Baseline Management

Baseline Information

Baseline Element Version Date Approver
Communication Schedule 1.0 August 11, 2025 Project Sponsor
Stakeholder Register 2.0 August 7, 2025 Project Sponsor
Communication Plan 1.0 August 7, 2025 Project Sponsor
R&R Matrix 1.0 August 11, 2025 Project Sponsor

Change Control Process

Change Request Procedure

  1. Identification: Change need identified by stakeholder or team member
  2. Documentation: Formal change request submitted
  3. Assessment: Impact analysis conducted
  4. Review: Change control board evaluation
  5. Decision: Approval or rejection with rationale
  6. Implementation: Approved changes implemented
  7. Communication: Change notification to stakeholders
  8. Update: Baseline documentation updated

Change Authority Matrix

Change Type Authority Approval Required
Minor Schedule Adjustments Project Manager Communications Lead
Stakeholder Contact Updates Communications Lead Project Manager
Communication Method Changes Communications Lead Steering Committee
Major Schedule Changes Steering Committee Project Sponsor
Stakeholder Role Changes Project Manager Project Sponsor
Communication Plan Revisions Steering Committee Project Sponsor

Implementation Guidelines

Schedule Activation

Pre-Implementation Checklist

Go-Live Process

  1. Week -1: Final preparation and system checks
  2. Day 1: Schedule activation and initial communications
  3. Week 1: Monitor and adjust based on initial feedback
  4. Month 1: Comprehensive review and optimization

Success Factors

Critical Success Factors

Success Indicators


Appendices

Appendix A: Communication Templates

Appendix B: Contact Directory

Appendix C: Technology Guide

Appendix D: Compliance Requirements


Document Status: BASELINED
Approved By: [Project Sponsor Name]
Date: August 11, 2025
Next Review: September 11, 2025


This Communication Schedule supports Activity A012 (WBS 1.1.2.1.4) and provides the detailed framework for stakeholder communication throughout the ICT Governance Framework implementation project.