Document Information | |
---|---|
Document Title | Communication Schedule |
Project | ICT Governance Framework |
Version | 1.0 |
Date | August 11, 2025 |
Author | Project Manager |
Reviewer | Communications Lead |
Approver | Project Sponsor |
WBS Code | 1.1.2.1.4 |
Activity ID | A012 |
Status | Baselined |
This Communication Schedule provides a detailed timeline and framework for all project communications throughout the ICT Governance Framework implementation. It defines specific communication events, frequencies, responsibilities, and deliverables to ensure consistent and effective stakeholder engagement.
Key Features:
Phase | Duration | Focus | Key Communications |
---|---|---|---|
Initiation | Weeks 1-4 | Project launch and stakeholder alignment | Kickoff, charter approval, initial briefings |
Planning | Weeks 5-12 | Detailed planning and stakeholder buy-in | Planning reviews, requirement validation, resource confirmation |
Execution | Weeks 13-40 | Implementation and progress tracking | Status reports, milestone updates, issue resolution |
Monitoring | Weeks 13-44 | Continuous oversight and adjustment | Performance dashboards, risk reviews, change communications |
Closure | Weeks 41-44 | Project completion and transition | Final reports, lessons learned, handover communications |
| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Project Kickoff Meeting | All Stakeholders | Project Manager | In-person/Virtual | 2 hours | | Wed | Executive Sponsor Briefing | Executive Sponsors | Project Manager | Presentation | 1 hour | | Fri | Team Formation Meeting | Core Project Team | Project Manager | In-person | 1.5 hours |
| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Stakeholder Registration Confirmation | All Stakeholders | Communications Lead | Email | N/A | | Wed | Steering Committee Formation | Steering Committee | Project Sponsor | Meeting | 1 hour | | Fri | Department Manager Briefings | Department Managers | Change Manager | Presentation | 45 min each |
| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Technical Team Orientation | Technical Team | Technical Lead | Workshop | 3 hours | | Wed | First Steering Committee Meeting | Steering Committee | Project Manager | Meeting | 2 hours | | Fri | Stakeholder Feedback Session | Key Stakeholders | Communications Lead | Survey/Interviews | Ongoing |
| Day | Communication Item | Audience | Owner | Format | Duration | |—–|——————-|———-|——-|——–|———-| | Mon | Project Charter Review | Executive Sponsors | Project Manager | Document Review | N/A | | Wed | Communication Plan Approval | Steering Committee | Communications Lead | Presentation | 30 min | | Fri | Phase 1 Completion Report | All Stakeholders | Project Manager | Email/Portal | N/A |
| Communication Item | Frequency | Day | Time | Audience | Owner | Format | |——————-|———–|—–|——|———-|——-|——–| | Project Status Meeting | Weekly | Monday | 9:00 AM | Core Team | Project Manager | Virtual Meeting | | Technical Working Group | Weekly | Wednesday | 2:00 PM | Technical Team | Technical Lead | Virtual Meeting | | Stakeholder Check-ins | Bi-weekly | Friday | Various | Key Stakeholders | Communications Lead | Phone/Email |
| Communication Item | Week | Audience | Owner | Format | |——————-|——|———-|——-|——–| | Steering Committee Meeting | Week 1 | Steering Committee | Project Manager | Meeting | | Executive Dashboard Update | Week 2 | Executive Sponsors | Project Manager | Dashboard | | Department Manager Briefing | Week 3 | Department Managers | Change Manager | Presentation | | All-Hands Project Update | Week 4 | All Stakeholders | Project Manager | Email/Intranet |
| Communication Item | Frequency | Time | Audience | Owner | Format | |——————-|———–|——|———-|——-|——–| | Team Stand-up | Daily | 8:30 AM | Core Team | Scrum Master | Virtual Meeting | | Issue Escalation (as needed) | As needed | Immediate | Relevant Stakeholders | Issue Owner | Phone/Email |
| Communication Item | Day | Time | Audience | Owner | Format | |——————-|—–|——|———-|——-|——–| | Project Status Report | Friday | 5:00 PM | All Stakeholders | Project Manager | Email/Portal | | Risk Review Meeting | Thursday | 10:00 AM | Risk Committee | Risk Manager | Virtual Meeting | | Technical Progress Review | Tuesday | 3:00 PM | Technical Team | Technical Lead | Virtual Meeting |
| Communication Item | Week | Audience | Owner | Format | |——————-|——|———-|——-|——–| | Executive Briefing | Odd weeks | Executive Sponsors | Project Manager | Presentation | | Change Impact Assessment | Even weeks | Affected Departments | Change Manager | Report |
| Communication Item | Week | Audience | Owner | Format | |——————-|——|———-|——-|——–| | Steering Committee Meeting | Week 1 | Steering Committee | Project Manager | Meeting | | Milestone Review | Week 2 | Key Stakeholders | Project Manager | Presentation | | Training Updates | Week 3 | End Users | Training Lead | Email/Intranet | | Vendor Coordination | Week 4 | External Vendors | Procurement Lead | Meeting |
| Communication Item | Frequency | Audience | Owner | Format | |——————-|———–|———-|——-|——–| | Performance Dashboard | Real-time | All Stakeholders | System Administrator | Online Dashboard | | Automated Alerts | As triggered | Relevant Stakeholders | Monitoring System | Email/SMS | | Health Check Reports | Weekly | Technical Team | Operations Lead | Report |
| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Project Closure Initiation | Core Team | Project Manager | Meeting | | Wed | Final Deliverable Review | Steering Committee | Project Manager | Presentation | | Fri | Transition Planning Meeting | Operations Team | Operations Lead | Meeting |
| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Lessons Learned Session | Project Team | Project Manager | Workshop | | Wed | Final Executive Briefing | Executive Sponsors | Project Manager | Presentation | | Fri | Knowledge Transfer Sessions | Support Teams | Technical Lead | Training |
| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Project Closure Report | All Stakeholders | Project Manager | Document | | Wed | Final Steering Committee | Steering Committee | Project Manager | Meeting | | Fri | Celebration Event | All Stakeholders | Project Manager | Event |
| Day | Communication Item | Audience | Owner | Format | |—–|——————-|———-|——-|——–| | Mon | Final Documentation Handover | Operations Team | Documentation Lead | Meeting | | Wed | Project Archive Completion | PMO | Project Manager | Process | | Fri | Post-Project Review | Steering Committee | Project Sponsor | Meeting |
Primary Responsibilities:
Communication Deliverables:
Authority Level: Full authority for routine communications; requires sponsor approval for external communications
Primary Responsibilities:
Communication Deliverables:
Authority Level: Authority for communication process and quality; escalates content decisions to Project Manager
Primary Responsibilities:
Communication Deliverables:
Authority Level: Full authority for technical communications; coordinates with Project Manager for business impact
Primary Responsibilities:
Communication Deliverables:
Authority Level: Authority for change-related communications; coordinates with Project Manager for timing
Primary Responsibilities:
Communication Deliverables:
Authority Level: Authority for risk communications; escalates critical risks to Project Manager
Communication Type | Preparer | Reviewer | Approver | Timeline |
---|---|---|---|---|
Executive Communications | Project Manager | Communications Lead | Project Sponsor | 3 business days |
External Communications | Communications Lead | Project Manager | Project Sponsor | 5 business days |
Technical Documentation | Technical Lead | Subject Matter Expert | Technical Lead | 2 business days |
Status Reports | Project Manager | Communications Lead | Project Manager | 1 business day |
Change Communications | Change Manager | Project Manager | Change Manager | 2 business days |
Risk Communications | Risk Manager | Project Manager | Risk Manager | 1 business day |
Training Materials | Training Lead | Subject Matter Expert | Training Lead | 3 business days |
Meeting Minutes | Meeting Scribe | Meeting Chair | Meeting Chair | 1 business day |
Metric | Target | Measurement Method | Frequency |
---|---|---|---|
Stakeholder Response Rate | >85% | Email responses, meeting attendance | Weekly |
Communication Satisfaction | >4.0/5.0 | Stakeholder surveys | Monthly |
Information Accuracy | >95% | Feedback analysis, error tracking | Monthly |
Timeliness Compliance | >90% | Schedule adherence tracking | Weekly |
Stakeholder Engagement Score | >4.2/5.0 | Engagement assessment surveys | Quarterly |
Metric | Target | Measurement Method | Frequency |
---|---|---|---|
Decision Speed | <3 days average | Decision tracking system | Monthly |
Issue Resolution Time | <5 days average | Issue management system | Weekly |
Change Request Processing | <7 days average | Change management system | Monthly |
Stakeholder Alignment | >80% agreement | Alignment surveys | Quarterly |
Communication ROI | Positive trend | Cost-benefit analysis | Quarterly |
Risk | Probability | Impact | Mitigation Strategy | Contingency Plan |
---|---|---|---|---|
Stakeholder Disengagement | Medium | High | Regular check-ins, personalized approach | Escalation to sponsor, direct intervention |
Information Overload | High | Medium | Targeted communications, summary formats | Simplified communications, key message focus |
Technical Communication Gaps | Medium | High | Technical liaison roles, translation support | Expert briefings, simplified documentation |
Geographic/Time Zone Challenges | High | Medium | Multiple time slots, recorded sessions | Asynchronous communication, regional coordinators |
Communication System Failures | Low | High | Backup systems, multiple channels | Manual processes, alternative platforms |
Baseline Element | Version | Date | Approver |
---|---|---|---|
Communication Schedule | 1.0 | August 11, 2025 | Project Sponsor |
Stakeholder Register | 2.0 | August 7, 2025 | Project Sponsor |
Communication Plan | 1.0 | August 7, 2025 | Project Sponsor |
R&R Matrix | 1.0 | August 11, 2025 | Project Sponsor |
Change Type | Authority | Approval Required |
---|---|---|
Minor Schedule Adjustments | Project Manager | Communications Lead |
Stakeholder Contact Updates | Communications Lead | Project Manager |
Communication Method Changes | Communications Lead | Steering Committee |
Major Schedule Changes | Steering Committee | Project Sponsor |
Stakeholder Role Changes | Project Manager | Project Sponsor |
Communication Plan Revisions | Steering Committee | Project Sponsor |
Document Status: BASELINED
Approved By: [Project Sponsor Name]
Date: August 11, 2025
Next Review: September 11, 2025
This Communication Schedule supports Activity A012 (WBS 1.1.2.1.4) and provides the detailed framework for stakeholder communication throughout the ICT Governance Framework implementation project.