ICT-Governance-Framework-Application

ICT Governance Framework - Activity Duration Estimates

Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Activity Duration Estimates
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025


Executive Summary

This document provides detailed duration estimates for all activities in the ICT Governance Framework project. Duration estimates are based on expert judgment, historical data, parametric estimation, and three-point estimation techniques. These estimates serve as the foundation for project scheduling, resource planning, and timeline management.

Project Investment: $1.275M Year 1 Expected Value: $2.3M Annual Total Project Duration: 65 weeks (15 months)

Estimation Methodology

Estimation Techniques Used

  1. Expert Judgment: Leveraging experience from similar governance projects
  2. Historical Data: Analysis of comparable project activities and durations
  3. Parametric Estimation: Using productivity rates and complexity factors
  4. Three-Point Estimation: Optimistic, Pessimistic, and Most Likely scenarios
  5. Bottom-Up Estimation: Detailed work package decomposition

Duration Calculation Formula

Expected Duration = (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6

Estimation Assumptions


PHASE 1: PROJECT INITIATION - Duration Estimates

Project Charter and Foundation Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A001 Define Project Scope and Objectives 3 days 5 days 8 days 5.2 days 5.2 7
A002 Develop Business Case and Value Proposition 5 days 8 days 12 days 8.2 days 8.2 10
A003 Identify Key Stakeholders and Sponsors 3 days 4 days 6 days 4.2 days 4.2 5
A004 Define Success Criteria and KPIs 4 days 6 days 9 days 6.2 days 6.2 8
A005 Analyze Organizational Strategic Objectives 5 days 7 days 10 days 7.2 days 7.2 9
A006 Map Governance Requirements to Business Goals 6 days 8 days 12 days 8.3 days 8.3 10
A007 Identify Regulatory and Compliance Requirements 7 days 9 days 13 days 9.3 days 9.3 12
A008 Validate Strategic Fit and Priority 2 days 3 days 5 days 3.2 days 3.2 4

Stakeholder Engagement Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A009 Identify All Project Stakeholders 3 days 5 days 8 days 5.2 days 5.2 7
A010 Analyze Stakeholder Influence and Interest 4 days 6 days 10 days 6.3 days 6.3 8
A011 Develop Stakeholder Engagement Strategies 5 days 7 days 11 days 7.3 days 7.3 9
A012 Create Stakeholder Register and Communication Plan 3 days 5 days 7 days 5.0 days 5.0 7
A013 Establish Communication Channels and Protocols 2 days 4 days 6 days 4.0 days 4.0 5
A014 Set Up Collaboration Platforms and Tools 4 days 6 days 10 days 6.3 days 6.3 8
A015 Create Communication Templates and Standards 2 days 3 days 5 days 3.2 days 3.2 4
A016 Implement Feedback and Escalation Mechanisms 2 days 4 days 6 days 4.0 days 4.0 5

Project Team Formation Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A017 Recruit and Assign Core Team Members 7 days 10 days 15 days 10.3 days 10.3 13
A018 Define Roles, Responsibilities, and RACI Matrix 3 days 4 days 6 days 4.2 days 4.2 5
A019 Establish Team Working Agreements and Protocols 2 days 3 days 5 days 3.2 days 3.2 4
A020 Conduct Team Orientation and Training 3 days 5 days 7 days 5.0 days 5.0 7

Phase 1 Total Duration: 20 work days (4 weeks calendar time)


PHASE 2: ANALYSIS AND DESIGN - Duration Estimates

Current State Assessment Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A021 Evaluate Current Governance Practices and Processes 10 days 15 days 22 days 15.3 days 15.3 19
A022 Assess Governance Maturity Against Industry Standards 8 days 10 days 14 days 10.3 days 10.3 13
A023 Identify Governance Gaps and Improvement Opportunities 10 days 12 days 16 days 12.3 days 12.3 15
A024 Document Current State Governance Architecture 6 days 8 days 12 days 8.3 days 8.3 10
A025 Inventory Existing Technology Assets and Systems 8 days 10 days 14 days 10.3 days 10.3 13
A026 Assess Current IT Architecture and Capabilities 10 days 12 days 16 days 12.3 days 12.3 15
A027 Evaluate Integration Requirements and Constraints 7 days 9 days 13 days 9.3 days 9.3 12
A028 Analyze Performance and Scalability Requirements 5 days 6 days 9 days 6.3 days 6.3 8

Requirements Analysis Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A029 Gather Stakeholder Requirements and Expectations 15 days 20 days 28 days 20.5 days 20.5 26
A030 Define Functional and Non-Functional Requirements 12 days 15 days 20 days 15.3 days 15.3 19
A031 Prioritize Requirements and Resolve Conflicts 6 days 8 days 12 days 8.3 days 8.3 10
A032 Create Comprehensive Requirements Documentation 8 days 10 days 14 days 10.3 days 10.3 13
A033 Identify Applicable Regulatory Frameworks 7 days 9 days 13 days 9.3 days 9.3 12
A034 Map Compliance Requirements to System Features 9 days 11 days 15 days 11.3 days 11.3 14

Solution Architecture Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A035 Design Target Governance Operating Model 12 days 15 days 20 days 15.3 days 15.3 19
A036 Define Governance Processes and Workflows 15 days 18 days 24 days 18.5 days 18.5 23
A037 Create Governance Roles and Responsibility Matrix 7 days 9 days 13 days 9.3 days 9.3 12
A038 Develop Governance Policies and Procedures 10 days 12 days 16 days 12.3 days 12.3 15
A039 Design System Architecture and Components 12 days 15 days 20 days 15.3 days 15.3 19
A040 Define Data Model and Information Architecture 10 days 12 days 16 days 12.3 days 12.3 15

Phase 2 Total Duration: 40 work days (8 weeks calendar time)


PHASE 3: DEVELOPMENT AND IMPLEMENTATION - Duration Estimates

Platform Development Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A061 Develop Governance Workflow Engine 30 days 40 days 55 days 40.8 days 40.8 51
A062 Implement User Management and Access Control 25 days 30 days 40 days 31.2 days 31.2 39
A063 Create Document and Policy Management System 20 days 25 days 35 days 26.2 days 26.2 33
A064 Build Notification and Communication Features 15 days 20 days 28 days 20.5 days 20.5 26
A065 Develop Data Collection and Processing Capabilities 25 days 30 days 40 days 31.2 days 31.2 39
A066 Implement Dashboard and Visualization Features 20 days 25 days 35 days 26.2 days 26.2 33
A067 Create Standard and Custom Reporting Functions 15 days 20 days 28 days 20.5 days 20.5 26
A068 Build Predictive Analytics and Insights Engine 18 days 23 days 30 days 23.3 days 23.3 29

Integration and Connectivity Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A069 Develop API and Integration Framework 25 days 30 days 40 days 31.2 days 31.2 39
A070 Implement Enterprise System Connectors 20 days 25 days 35 days 26.2 days 26.2 33
A071 Create Data Synchronization and Management 15 days 20 days 28 days 20.5 days 20.5 26
A072 Build Monitoring and Health Check Capabilities 12 days 15 days 20 days 15.3 days 15.3 19

Quality Assurance Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A073 Develop Testing Strategy and Plans 8 days 10 days 14 days 10.3 days 10.3 13
A074 Create Test Cases and Test Data 12 days 15 days 20 days 15.3 days 15.3 19
A075 Execute Unit and Integration Testing 15 days 20 days 28 days 20.5 days 20.5 26
A076 Perform System and End-to-End Testing 18 days 25 days 35 days 26.2 days 26.2 33
A077 Conduct User Acceptance Testing 12 days 15 days 20 days 15.3 days 15.3 19
A078 Validate Performance and Security 10 days 12 days 16 days 12.3 days 12.3 15

Phase 3 Total Duration: 100 work days (20 weeks calendar time)


PHASE 4: DEPLOYMENT AND ROLLOUT - Duration Estimates

Infrastructure Preparation Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A121 Provision and Configure Production Infrastructure 12 days 15 days 20 days 15.3 days 15.3 19
A122 Install and Configure Software Components 10 days 12 days 16 days 12.3 days 12.3 15
A123 Implement Security Controls and Monitoring 8 days 10 days 14 days 10.3 days 10.3 13
A124 Conduct Infrastructure Testing and Validation 6 days 8 days 12 days 8.3 days 8.3 10

Data Migration Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A125 Prepare and Validate Data Migration Procedures 8 days 10 days 14 days 10.3 days 10.3 13
A126 Execute Data Migration and Transformation 10 days 12 days 16 days 12.3 days 12.3 15
A127 Validate Data Integrity and Completeness 6 days 8 days 12 days 8.3 days 8.3 10

Pilot and Rollout Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A128 Plan and Setup Pilot Program 5 days 7 days 11 days 7.3 days 7.3 9
A129 Execute Pilot and Collect Feedback 8 days 10 days 14 days 10.3 days 10.3 13
A130 Analyze Pilot Results and Implement Improvements 5 days 7 days 11 days 7.3 days 7.3 9
A131 Conduct Production Deployment 3 days 5 days 8 days 5.2 days 5.2 7
A132 Execute User Training and Onboarding 10 days 15 days 22 days 15.3 days 15.3 19
A133 Provide Go-Live Support and Stabilization 8 days 12 days 18 days 12.3 days 12.3 15

Phase 4 Total Duration: 40 work days (8 weeks calendar time)


PHASE 5: PROJECT CLOSURE - Duration Estimates

Project Completion Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A161 Validate All Project Deliverables and Outcomes 8 days 10 days 14 days 10.3 days 10.3 13
A162 Obtain Formal Acceptance from Stakeholders 4 days 6 days 10 days 6.3 days 6.3 8
A163 Complete Final Testing and Quality Assurance 6 days 8 days 12 days 8.3 days 8.3 10
A164 Document Final Project Status and Metrics 3 days 4 days 6 days 4.2 days 4.2 5

Success Validation Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A165 Measure Achievement Against Success Criteria 5 days 7 days 11 days 7.3 days 7.3 9
A166 Validate Business Value and ROI Realization 4 days 6 days 10 days 6.3 days 6.3 8
A167 Assess Stakeholder Satisfaction and Feedback 3 days 5 days 7 days 5.0 days 5.0 7
A168 Document Lessons Learned and Best Practices 3 days 4 days 6 days 4.2 days 4.2 5

Knowledge Transfer Activities

Activity ID Activity Name Optimistic Most Likely Pessimistic Expected Duration Work Days Calendar Days
A169 Transfer Operational Knowledge to Support Teams 7 days 9 days 13 days 9.3 days 9.3 12
A170 Conduct Handover Sessions and Documentation Review 4 days 6 days 10 days 6.3 days 6.3 8

Phase 5 Total Duration: 15 work days (3 weeks calendar time)


Duration Summary and Analysis

Project Duration Summary

Phase Work Days Calendar Weeks % of Total Duration
Project Initiation 20 4 12.3%
Analysis and Design 40 8 24.6%
Development and Implementation 100 20 61.5%
Deployment and Rollout 40 8 24.6%
Project Closure 15 3 9.2%
Total Project Duration 325 65 100%

Critical Path Analysis

Critical Path Activities (longest sequence):

  1. Project Foundation (A001-A008): 4 weeks
  2. Requirements and Architecture (A029-A040): 16 weeks
  3. Core Development (A061-A072): 32 weeks
  4. Deployment and Rollout (A121-A133): 8 weeks
  5. Project Closure (A161-A170): 3 weeks

Total Critical Path Duration: 63 weeks (15.7 months)

Duration Risk Analysis

High-Risk Activities (High Variance)

Medium-Risk Activities (Moderate Variance)

Low-Risk Activities (Low Variance)

Duration Optimization Opportunities

Fast-Track Opportunities

Resource Acceleration Options


Duration Estimation Confidence Levels

Confidence Level by Phase

Phase Confidence Level Rationale
Project Initiation High (85%) Well-defined activities with historical precedent
Analysis and Design Medium-High (75%) Some stakeholder and complexity variables
Development and Implementation Medium (65%) Technical complexity and integration challenges
Deployment and Rollout Medium-High (75%) Proven deployment methodologies
Project Closure High (90%) Standard closure processes and activities

Overall Project Confidence

Confidence Factors


Duration Management Guidelines

Schedule Monitoring

Duration Variance Management

Schedule Compression Techniques

Buffer Management


Quality Considerations

Duration vs. Quality Trade-offs

Duration Estimation Accuracy


Conclusion

These activity duration estimates provide a comprehensive foundation for project scheduling and timeline management. The estimates reflect realistic timeframes based on project complexity, resource capabilities, and quality requirements. With a total estimated duration of 65 weeks (15 months), the project aligns with the planned timeline for delivering the $2.3M annual value proposition.

Key Success Factors:

The duration estimates enable realistic project scheduling while maintaining focus on quality deliverables and successful achievement of project objectives.


Document Control:


These duration estimates support realistic project planning and timeline management, enabling successful delivery of the ICT Governance Framework transformation within planned timeframes and quality standards.