ICT Governance Framework - Activity Duration Estimates
Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Activity Duration Estimates
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025
Executive Summary
This document provides detailed duration estimates for all activities in the ICT Governance Framework project. Duration estimates are based on expert judgment, historical data, parametric estimation, and three-point estimation techniques. These estimates serve as the foundation for project scheduling, resource planning, and timeline management.
Project Investment: $1.275M Year 1 |
Expected Value: $2.3M Annual |
Total Project Duration: 65 weeks (15 months) |
Estimation Methodology
Estimation Techniques Used
- Expert Judgment: Leveraging experience from similar governance projects
- Historical Data: Analysis of comparable project activities and durations
- Parametric Estimation: Using productivity rates and complexity factors
- Three-Point Estimation: Optimistic, Pessimistic, and Most Likely scenarios
- Bottom-Up Estimation: Detailed work package decomposition
Expected Duration = (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6
Estimation Assumptions
- Standard Work Week: 40 hours (5 days × 8 hours)
- Resource Productivity: Industry-standard productivity rates
- Organizational Maturity: Medium maturity level for change adoption
- External Dependencies: Normal response times for external parties
- Quality Standards: High-quality deliverables with thorough review processes
PHASE 1: PROJECT INITIATION - Duration Estimates
Project Charter and Foundation Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A001 |
Define Project Scope and Objectives |
3 days |
5 days |
8 days |
5.2 days |
5.2 |
7 |
A002 |
Develop Business Case and Value Proposition |
5 days |
8 days |
12 days |
8.2 days |
8.2 |
10 |
A003 |
Identify Key Stakeholders and Sponsors |
3 days |
4 days |
6 days |
4.2 days |
4.2 |
5 |
A004 |
Define Success Criteria and KPIs |
4 days |
6 days |
9 days |
6.2 days |
6.2 |
8 |
A005 |
Analyze Organizational Strategic Objectives |
5 days |
7 days |
10 days |
7.2 days |
7.2 |
9 |
A006 |
Map Governance Requirements to Business Goals |
6 days |
8 days |
12 days |
8.3 days |
8.3 |
10 |
A007 |
Identify Regulatory and Compliance Requirements |
7 days |
9 days |
13 days |
9.3 days |
9.3 |
12 |
A008 |
Validate Strategic Fit and Priority |
2 days |
3 days |
5 days |
3.2 days |
3.2 |
4 |
Stakeholder Engagement Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A009 |
Identify All Project Stakeholders |
3 days |
5 days |
8 days |
5.2 days |
5.2 |
7 |
A010 |
Analyze Stakeholder Influence and Interest |
4 days |
6 days |
10 days |
6.3 days |
6.3 |
8 |
A011 |
Develop Stakeholder Engagement Strategies |
5 days |
7 days |
11 days |
7.3 days |
7.3 |
9 |
A012 |
Create Stakeholder Register and Communication Plan |
3 days |
5 days |
7 days |
5.0 days |
5.0 |
7 |
A013 |
Establish Communication Channels and Protocols |
2 days |
4 days |
6 days |
4.0 days |
4.0 |
5 |
A014 |
Set Up Collaboration Platforms and Tools |
4 days |
6 days |
10 days |
6.3 days |
6.3 |
8 |
A015 |
Create Communication Templates and Standards |
2 days |
3 days |
5 days |
3.2 days |
3.2 |
4 |
A016 |
Implement Feedback and Escalation Mechanisms |
2 days |
4 days |
6 days |
4.0 days |
4.0 |
5 |
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A017 |
Recruit and Assign Core Team Members |
7 days |
10 days |
15 days |
10.3 days |
10.3 |
13 |
A018 |
Define Roles, Responsibilities, and RACI Matrix |
3 days |
4 days |
6 days |
4.2 days |
4.2 |
5 |
A019 |
Establish Team Working Agreements and Protocols |
2 days |
3 days |
5 days |
3.2 days |
3.2 |
4 |
A020 |
Conduct Team Orientation and Training |
3 days |
5 days |
7 days |
5.0 days |
5.0 |
7 |
Phase 1 Total Duration: 20 work days (4 weeks calendar time)
PHASE 2: ANALYSIS AND DESIGN - Duration Estimates
Current State Assessment Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A021 |
Evaluate Current Governance Practices and Processes |
10 days |
15 days |
22 days |
15.3 days |
15.3 |
19 |
A022 |
Assess Governance Maturity Against Industry Standards |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A023 |
Identify Governance Gaps and Improvement Opportunities |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
A024 |
Document Current State Governance Architecture |
6 days |
8 days |
12 days |
8.3 days |
8.3 |
10 |
A025 |
Inventory Existing Technology Assets and Systems |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A026 |
Assess Current IT Architecture and Capabilities |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
A027 |
Evaluate Integration Requirements and Constraints |
7 days |
9 days |
13 days |
9.3 days |
9.3 |
12 |
A028 |
Analyze Performance and Scalability Requirements |
5 days |
6 days |
9 days |
6.3 days |
6.3 |
8 |
Requirements Analysis Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A029 |
Gather Stakeholder Requirements and Expectations |
15 days |
20 days |
28 days |
20.5 days |
20.5 |
26 |
A030 |
Define Functional and Non-Functional Requirements |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
A031 |
Prioritize Requirements and Resolve Conflicts |
6 days |
8 days |
12 days |
8.3 days |
8.3 |
10 |
A032 |
Create Comprehensive Requirements Documentation |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A033 |
Identify Applicable Regulatory Frameworks |
7 days |
9 days |
13 days |
9.3 days |
9.3 |
12 |
A034 |
Map Compliance Requirements to System Features |
9 days |
11 days |
15 days |
11.3 days |
11.3 |
14 |
Solution Architecture Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A035 |
Design Target Governance Operating Model |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
A036 |
Define Governance Processes and Workflows |
15 days |
18 days |
24 days |
18.5 days |
18.5 |
23 |
A037 |
Create Governance Roles and Responsibility Matrix |
7 days |
9 days |
13 days |
9.3 days |
9.3 |
12 |
A038 |
Develop Governance Policies and Procedures |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
A039 |
Design System Architecture and Components |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
A040 |
Define Data Model and Information Architecture |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
Phase 2 Total Duration: 40 work days (8 weeks calendar time)
PHASE 3: DEVELOPMENT AND IMPLEMENTATION - Duration Estimates
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A061 |
Develop Governance Workflow Engine |
30 days |
40 days |
55 days |
40.8 days |
40.8 |
51 |
A062 |
Implement User Management and Access Control |
25 days |
30 days |
40 days |
31.2 days |
31.2 |
39 |
A063 |
Create Document and Policy Management System |
20 days |
25 days |
35 days |
26.2 days |
26.2 |
33 |
A064 |
Build Notification and Communication Features |
15 days |
20 days |
28 days |
20.5 days |
20.5 |
26 |
A065 |
Develop Data Collection and Processing Capabilities |
25 days |
30 days |
40 days |
31.2 days |
31.2 |
39 |
A066 |
Implement Dashboard and Visualization Features |
20 days |
25 days |
35 days |
26.2 days |
26.2 |
33 |
A067 |
Create Standard and Custom Reporting Functions |
15 days |
20 days |
28 days |
20.5 days |
20.5 |
26 |
A068 |
Build Predictive Analytics and Insights Engine |
18 days |
23 days |
30 days |
23.3 days |
23.3 |
29 |
Integration and Connectivity Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A069 |
Develop API and Integration Framework |
25 days |
30 days |
40 days |
31.2 days |
31.2 |
39 |
A070 |
Implement Enterprise System Connectors |
20 days |
25 days |
35 days |
26.2 days |
26.2 |
33 |
A071 |
Create Data Synchronization and Management |
15 days |
20 days |
28 days |
20.5 days |
20.5 |
26 |
A072 |
Build Monitoring and Health Check Capabilities |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
Quality Assurance Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A073 |
Develop Testing Strategy and Plans |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A074 |
Create Test Cases and Test Data |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
A075 |
Execute Unit and Integration Testing |
15 days |
20 days |
28 days |
20.5 days |
20.5 |
26 |
A076 |
Perform System and End-to-End Testing |
18 days |
25 days |
35 days |
26.2 days |
26.2 |
33 |
A077 |
Conduct User Acceptance Testing |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
A078 |
Validate Performance and Security |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
Phase 3 Total Duration: 100 work days (20 weeks calendar time)
PHASE 4: DEPLOYMENT AND ROLLOUT - Duration Estimates
Infrastructure Preparation Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A121 |
Provision and Configure Production Infrastructure |
12 days |
15 days |
20 days |
15.3 days |
15.3 |
19 |
A122 |
Install and Configure Software Components |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
A123 |
Implement Security Controls and Monitoring |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A124 |
Conduct Infrastructure Testing and Validation |
6 days |
8 days |
12 days |
8.3 days |
8.3 |
10 |
Data Migration Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A125 |
Prepare and Validate Data Migration Procedures |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A126 |
Execute Data Migration and Transformation |
10 days |
12 days |
16 days |
12.3 days |
12.3 |
15 |
A127 |
Validate Data Integrity and Completeness |
6 days |
8 days |
12 days |
8.3 days |
8.3 |
10 |
Pilot and Rollout Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A128 |
Plan and Setup Pilot Program |
5 days |
7 days |
11 days |
7.3 days |
7.3 |
9 |
A129 |
Execute Pilot and Collect Feedback |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A130 |
Analyze Pilot Results and Implement Improvements |
5 days |
7 days |
11 days |
7.3 days |
7.3 |
9 |
A131 |
Conduct Production Deployment |
3 days |
5 days |
8 days |
5.2 days |
5.2 |
7 |
A132 |
Execute User Training and Onboarding |
10 days |
15 days |
22 days |
15.3 days |
15.3 |
19 |
A133 |
Provide Go-Live Support and Stabilization |
8 days |
12 days |
18 days |
12.3 days |
12.3 |
15 |
Phase 4 Total Duration: 40 work days (8 weeks calendar time)
PHASE 5: PROJECT CLOSURE - Duration Estimates
Project Completion Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A161 |
Validate All Project Deliverables and Outcomes |
8 days |
10 days |
14 days |
10.3 days |
10.3 |
13 |
A162 |
Obtain Formal Acceptance from Stakeholders |
4 days |
6 days |
10 days |
6.3 days |
6.3 |
8 |
A163 |
Complete Final Testing and Quality Assurance |
6 days |
8 days |
12 days |
8.3 days |
8.3 |
10 |
A164 |
Document Final Project Status and Metrics |
3 days |
4 days |
6 days |
4.2 days |
4.2 |
5 |
Success Validation Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A165 |
Measure Achievement Against Success Criteria |
5 days |
7 days |
11 days |
7.3 days |
7.3 |
9 |
A166 |
Validate Business Value and ROI Realization |
4 days |
6 days |
10 days |
6.3 days |
6.3 |
8 |
A167 |
Assess Stakeholder Satisfaction and Feedback |
3 days |
5 days |
7 days |
5.0 days |
5.0 |
7 |
A168 |
Document Lessons Learned and Best Practices |
3 days |
4 days |
6 days |
4.2 days |
4.2 |
5 |
Knowledge Transfer Activities
Activity ID |
Activity Name |
Optimistic |
Most Likely |
Pessimistic |
Expected Duration |
Work Days |
Calendar Days |
A169 |
Transfer Operational Knowledge to Support Teams |
7 days |
9 days |
13 days |
9.3 days |
9.3 |
12 |
A170 |
Conduct Handover Sessions and Documentation Review |
4 days |
6 days |
10 days |
6.3 days |
6.3 |
8 |
Phase 5 Total Duration: 15 work days (3 weeks calendar time)
Duration Summary and Analysis
Project Duration Summary
Phase |
Work Days |
Calendar Weeks |
% of Total Duration |
Project Initiation |
20 |
4 |
12.3% |
Analysis and Design |
40 |
8 |
24.6% |
Development and Implementation |
100 |
20 |
61.5% |
Deployment and Rollout |
40 |
8 |
24.6% |
Project Closure |
15 |
3 |
9.2% |
Total Project Duration |
325 |
65 |
100% |
Critical Path Analysis
Critical Path Activities (longest sequence):
- Project Foundation (A001-A008): 4 weeks
- Requirements and Architecture (A029-A040): 16 weeks
- Core Development (A061-A072): 32 weeks
- Deployment and Rollout (A121-A133): 8 weeks
- Project Closure (A161-A170): 3 weeks
Total Critical Path Duration: 63 weeks (15.7 months)
Duration Risk Analysis
High-Risk Activities (High Variance)
- A029 - Gather Stakeholder Requirements: 13-day variance (stakeholder availability)
- A061 - Develop Governance Workflow Engine: 25-day variance (technical complexity)
- A076 - System and End-to-End Testing: 17-day variance (defect discovery)
- A132 - User Training and Onboarding: 12-day variance (change resistance)
Medium-Risk Activities (Moderate Variance)
- A036 - Define Governance Processes: 9-day variance (stakeholder consensus)
- A069 - Develop API Framework: 15-day variance (integration complexity)
- A126 - Data Migration Execution: 6-day variance (data quality issues)
Low-Risk Activities (Low Variance)
- A018 - Define RACI Matrix: 3-day variance (well-defined process)
- A164 - Document Project Status: 3-day variance (routine documentation)
- A167 - Stakeholder Satisfaction Survey: 4-day variance (standard process)
Duration Optimization Opportunities
Fast-Track Opportunities
- Parallel Requirements Gathering: Run functional and compliance requirements in parallel (Save 5 days)
- Overlapped Development: Start development of independent modules before complete design (Save 10 days)
- Concurrent Testing: Execute different testing types in parallel (Save 8 days)
Resource Acceleration Options
- Additional Development Resources: Add developers to complex activities (Reduce 15 days)
- Dedicated Integration Team: Parallel integration development (Reduce 8 days)
- Extended Testing Team: Accelerate testing activities (Reduce 5 days)
Duration Estimation Confidence Levels
Confidence Level by Phase
Phase |
Confidence Level |
Rationale |
Project Initiation |
High (85%) |
Well-defined activities with historical precedent |
Analysis and Design |
Medium-High (75%) |
Some stakeholder and complexity variables |
Development and Implementation |
Medium (65%) |
Technical complexity and integration challenges |
Deployment and Rollout |
Medium-High (75%) |
Proven deployment methodologies |
Project Closure |
High (90%) |
Standard closure processes and activities |
Overall Project Confidence
- Most Likely Scenario: 65 weeks (15 months) - 70% confidence
- Optimistic Scenario: 52 weeks (12 months) - 15% confidence
- Pessimistic Scenario: 82 weeks (19 months) - 15% confidence
Confidence Factors
- Positive Factors: Experienced team, proven methodologies, strong executive support
- Risk Factors: Technical complexity, stakeholder coordination, integration challenges
- Mitigation Strategies: Regular risk reviews, contingency planning, resource flexibility
Duration Management Guidelines
Schedule Monitoring
- Weekly Progress Reviews: Track actual vs. planned duration for active activities
- Monthly Schedule Updates: Update remaining duration estimates based on progress
- Milestone Reviews: Validate duration estimates at major project milestones
- Critical Path Focus: Monitor critical path activities for schedule impact
Duration Variance Management
- ±10% Variance: Normal variance requiring no action
- ±20% Variance: Investigate causes and implement corrective action
- >20% Variance: Escalate to steering committee and revise project schedule
Schedule Compression Techniques
- Fast Tracking: Parallel execution of normally sequential activities
- Crashing: Adding resources to reduce activity duration
- Scope Reduction: Reducing activity scope while maintaining deliverable quality
- Resource Reallocation: Moving resources from non-critical to critical activities
Buffer Management
- Project Buffer: 10% buffer included at project level (6.5 weeks)
- Phase Buffers: 5% buffer at end of each major phase
- Critical Activity Buffer: Individual buffers for high-risk activities
- Resource Buffer: Contingency resources for schedule recovery
Quality Considerations
Duration vs. Quality Trade-offs
- Minimum Duration Standards: Quality gates that cannot be compressed
- Review and Approval Time: Built-in time for stakeholder reviews
- Rework Allowance: Expected rework time based on historical data
- Testing Adequacy: Sufficient testing time to ensure quality deliverables
Duration Estimation Accuracy
- Early Estimates: ±50% accuracy during initiation phase
- Refined Estimates: ±25% accuracy during planning phase
- Detailed Estimates: ±10% accuracy during execution phase
- Final Estimates: ±5% accuracy near activity completion
Conclusion
These activity duration estimates provide a comprehensive foundation for project scheduling and timeline management. The estimates reflect realistic timeframes based on project complexity, resource capabilities, and quality requirements. With a total estimated duration of 65 weeks (15 months), the project aligns with the planned timeline for delivering the $2.3M annual value proposition.
Key Success Factors:
- Proactive management of high-risk activities
- Regular monitoring and updating of duration estimates
- Effective coordination of stakeholder dependencies
- Flexible resource allocation to address schedule challenges
The duration estimates enable realistic project scheduling while maintaining focus on quality deliverables and successful achievement of project objectives.
Document Control:
- Integration: Activity List, Project Schedule, Resource Management Plan
- Dependencies: Work Breakdown Structure, Risk Management Plan, Quality Management Plan
- Review Cycle: Updated monthly during project execution based on actual progress
- Ownership: Project Manager with input from all activity owners and subject matter experts
These duration estimates support realistic project planning and timeline management, enabling successful delivery of the ICT Governance Framework transformation within planned timeframes and quality standards.