ICT-Governance-Framework-Application

ICT Governance Framework - Activity List

Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Activity List
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025


Executive Summary

This Activity List provides a comprehensive enumeration of all specific activities required to complete the ICT Governance Framework project. Each activity is derived from the Work Breakdown Structure (WBS) and includes detailed specifications for scheduling, resource planning, and progress tracking.

Project Investment: $1.275M Year 1 Expected Value: $2.3M Annual Project Duration: 15 months

Activity List Structure

Activities are organized by WBS hierarchy and include:


Global Defaults and Field Definitions

To reduce repetition and improve scheduling quality, the following defaults apply unless an activity explicitly overrides them.

Field definitions (for consistency across tools):

Deliverable links cross-reference (key examples):

PHASE 1: PROJECT INITIATION (Activities 1-20)

Project Charter and Foundation Activities

Activity ID: A001

Activity ID: A002

Activity ID: A003

Activity ID: A004

Activity ID: A005

Activity ID: A006

Activity ID: A007

Activity ID: A008

Stakeholder Engagement Activities

Activity ID: A009

Activity ID: A010

Activity ID: A011

Activity ID: A012

Activity ID: A013COMPLETED

Activity ID: A014

Activity ID: A015

Activity ID: A016

Project Team Formation Activities

Activity ID: A017

Activity ID: A018

Activity ID: A019

Activity ID: A020


PHASE 2: ANALYSIS AND DESIGN (Activities 21-60)

Current State Assessment Activities

Activity ID: A021

Activity ID: A022

Activity ID: A023

Activity ID: A024

Activity ID: A025

Activity ID: A026

Activity ID: A027

Activity ID: A028

Requirements Analysis Activities

Activity ID: A029

Activity ID: A030

Activity ID: A031

Activity ID: A032

Activity ID: A033

Activity ID: A034

Solution Architecture Activities

Activity ID: A035

Activity ID: A036

Activity ID: A037

Activity ID: A038

Activity ID: A039

Activity ID: A040


PHASE 3: DEVELOPMENT AND IMPLEMENTATION (Activities 61-120)

Platform Development Activities

Activity ID: A061

Activity ID: A062

Activity ID: A063

Activity ID: A064

Activity ID: A065

Activity ID: A066

Activity ID: A067

Activity ID: A068

Integration and Connectivity Activities

Activity ID: A069

Activity ID: A070

Activity ID: A071

Activity ID: A072


PHASE 4: DEPLOYMENT AND ROLLOUT (Activities 121-160)

Infrastructure and Deployment Activities

Activity ID: A121

Activity ID: A122

Activity ID: A123

Activity ID: A124

Data Migration Activities

Activity ID: A125

Activity ID: A126

Activity ID: A127


PHASE 5: PROJECT CLOSURE (Activities 161-180)

Project Completion Activities

Activity ID: A161

Activity ID: A162

Activity ID: A163

Activity ID: A164

Success Validation Activities

Activity ID: A165

Activity ID: A166

Activity ID: A167

Activity ID: A168

Knowledge Transfer and Documentation Activities

Activity ID: A169

Activity ID: A170


Activity Summary Statistics

Total Project Activities

Enumerated Activities in this document: 69 (of planned 180) Planned Total Activities (program baseline): 180

Activities by Phase

| Phase | Activities | Effort (Hours) | Duration (Weeks) | |——-|————|—————-|——————| | Initiation | 20 | 960 | 4 | | Analysis & Design | 40 | 3,200 | 8 | | Development & Implementation | 60 | 8,000 | 20 | | Deployment & Rollout | 40 | 3,200 | 8 | | Project Closure | 20 | 640 | 3 |

Critical Path Activities

Key activities on the critical path that drive project timeline:

Resource Allocation Summary


Activity Dependencies and Relationships

Dependency Types

Critical Dependencies

External Dependencies


Usage Guidelines

Project Scheduling

Resource Planning

Progress Tracking


Conclusion

This comprehensive Activity List provides the detailed foundation for project scheduling, resource allocation, and progress tracking for the ICT Governance Framework project. With 180 specific activities totaling 16,000 hours of effort, the list enables precise project planning and control to deliver the $2.3M annual value proposition.

The Activity List serves as the detailed roadmap for systematic project execution, ensuring all work components are properly planned, resourced, and tracked for successful delivery.


Document Control:


This Activity List enables detailed project planning and control, supporting successful delivery of the ICT Governance Framework transformation initiative within planned time, budget, and quality parameters.


Acceptance Criteria, Dependency Types, and Risks (Appendix)

Notes:

Phase 1 — Initiation (A001–A020)

Phase 2 — Analysis & Design (A021–A040)

Phase 3 — Dev & Implementation (A061–A072)

Phase 3 — Integration (A069–A072)

Phase 4 — Deployment (A121–A127)

Phase 5 — Closure (A161–A170)


Per-Activity Summary, Context, Acceptance, Other (Tables)

Phase 1 — Initiation (A001–A020)

Activity Summary Context Acceptance Criteria Other Information
A001 Define scope and objectives Project start; feeds Charter (../project-charter/project-charter.md) Scope statement approved; exclusions baselined Risk: scope creep; enforce change control
A002 Build business case & value After A001; aligns to ../core-analysis/business-case.md Sponsor/Finance approve ROI/NPV Link benefits to KPI docs; assumptions logged
A003 Identify stakeholders/sponsors After A001; create ../stakeholder-management/stakeholder-register.md >95% coverage; governance bodies noted Protect PII; version register
A004 Define success criteria & KPIs After A002; use ../../Target-Governance-Framework-KPIs-Metrics.md KPI set baselined with owners/sources Dashboard mapping in ../../ICT-Governance-Transparency-Dashboard.md
A005 Analyze org strategic objectives After A003; cross-check strategic statements Alignment analysis approved Conflicts escalated to Sponsor
A006 Map governance to business goals After A005; create mapping matrix Mapping signed off; RTM entries added Trace to requirements and controls
A007 Identify regulatory & compliance After A005; compile matrix Legal sign-off on applicability Watchlist for regulatory change
A008 Validate strategic fit & priority After A006/A007; stage gate Exec approval minute recorded Budget/resources confirmed
A009 Identify all stakeholders After A003; broaden discovery PMO validates list completeness Add discovery method notes
A010 Analyze influence & interest After A009; build grid Grid approved by PM & Sponsor Mitigate bias via peer review
A011 Develop engagement strategies After A010; per persona/group Strategies approved by Sponsor Include cadence and channels
A012 Create register & comms plan After A011; comms plan in ../management-plans/communication-management-plan.md Plan baselined; roles set Include feedback loop
A013 Establish comms protocols After A012; define SLAs & escalation Protocols published Security and retention requirements
A014 Set up collaboration tools After A013; configure M365/DevOps Platforms configured; access audited Audit logging enabled
A015 Create comms templates/standards After A013; use ../templates/document-template.md Templates adopted org-wide Enforce via linting/PR checks
A016 Implement feedback/escalation After A014; enable intake System operational; SLAs defined Runbooks for triage and escalation
A017 Recruit & assign core team After A008; staff project Roster filled; access provisioned Plan for backfills
A018 Define roles & RACI After A017; publish RACI RACI approved; decision rights documented Add DACI notes if used
A019 Establish team agreements After A018; team charter Charter signed by team Quarterly refresh scheduled
A020 Conduct orientation/training After A019; onboarding Attendance complete; competency checks passed Record training evidence

Phase 2 — Analysis & Design (A021–A040)

Activity Summary Context Acceptance Criteria Other Information
A021 Assess current governance After A020; baseline maturity Assessment report approved Include process inventory
A022 Score against frameworks After A021; COBIT/ITIL/ISO Maturity scores baselined Scoring rubric attached
A023 Identify gaps & opportunities After A022; prioritize Gap list prioritized; heatmap produced Feed risk register
A024 Document current architecture After A021; C4/BPMN/flows Diagrams published & versioned Include trust boundaries
A025 Inventory tech assets After A020; CMDB et al. ≥95% coverage of tier‑1 Reconcile discrepancies
A026 Assess IT architecture After A025; non-functionals Constraints documented & approved Link to system-design-specification.md
A027 Evaluate integration reqs After A026; interfaces Integration requirements approved Contract-first, OpenAPI
A028 Analyze performance & scale After A026; capacity Perf targets & capacity plan approved Link to performance-requirements.md
A029 Elicit stakeholder requirements After A012; interviews/workshops Elicitation artifacts complete; sign-offs Retain raw notes policy
A030 Define F/NFR requirements After A029; SRS F/NFRs testable and reviewed Single SRS source of truth
A031 Prioritize & resolve conflicts After A030; MoSCoW Prioritized backlog; conflicts resolved Decisions logged
A032 Compile requirements docs After A031; RTM SRS complete; RTM updated Acceptance criteria included
A033 Identify regulatory frameworks After A007; inventory Regulatory inventory signed-off Cite sources & jurisdictions
A034 Map compliance to features After A033/A032; mapping Mapping approved; verification steps defined Add control tests
A035 Design target operating model After A023/A032; TOM TOM approved Capability targets set
A036 Define governance processes After A035; BPMN Processes/workflows approved Decision matrices/thresholds
A037 Create roles & responsibility After A035; org model Roles/RACI ratified Align to Entra ID roles
A038 Develop policies & procedures After A036/A037; manuals Policies/procedures approved Exceptions/waivers process
A039 Design system architecture After A027/A032; C4/ADRs System architecture baselined Interface contracts defined
A040 Define data model & IA After A032; DMBOK Data model & governance plan approved Data classification & lineage

Phase 3 — Development & Implementation (A061–A068)

Activity Summary Context Acceptance Criteria Other Information
A061 Build workflow engine After A036/A039; core engine Meets throughput/SLA; DOR/DOD set Config-as-code; profiling
A062 Implement RBAC & user mgmt After A037/A039; security RBAC enforced; audit logs enabled Map to Entra ID
A063 Document/policy management After A038/A061; DMS Versioning, approvals, retention functional Audit trails
A064 Notifications & comms After A062; alerts Reliable delivery; escalation rules Throttling & idempotency
A065 Data collection & processing After A040; pipelines DQ checks pass; processing stable PII controls
A066 Dashboards & visualization After A065; exec/ops views Performance/accessibility met; sign-off Align to transparency dashboard
A067 Reporting functions After A065; catalog Standard/custom reports delivered; RLS Report catalog maintained
A068 Predictive analytics engine After A065; ML Drift monitoring enabled; insights validated Explainability & MLOps

Phase 3 — Integration & Connectivity (A069–A072)

Activity Summary Context Acceptance Criteria Other Information
A069 API & integration framework After A039; standards Framework documented; security tested OpenAPI, versioning, OAuth2/MTLS
A070 Enterprise connectors After A069/A027; adapters Connectors meet SLAs Retry/circuit breaker
A071 Data sync & MDM After A070; golden record Sync correctness; MDM rules validated Conflict resolution rules
A072 Monitoring & health checks After A071; observability SLOs defined; runbooks in place OpenTelemetry, alert routing

Phase 4 — Deployment & Rollout (A121–A127)

Activity Summary Context Acceptance Criteria Other Information
A121 Provision production infra After A072; IaC Infra provisioned; baselines applied Tagging/cost governance
A122 Install/config software After A121; release Deployed; config externalized Key Vault; back-out plan
A123 Security controls & monitoring After A122; controls Controls operational; SIEM integrated Map to NIST/ISO
A124 Infra testing & validation After A123; perf/chaos SLOs met under load Tuning captured
A125 Prepare data migration After A124; procedures Rehearsal passed; rollback tested Data mapping controlled
A126 Execute migration After A125; execution Migration executed; logs complete Handling long-running jobs
A127 Validate data integrity After A126; QC Integrity verified; business sign-off Sampling plan

Phase 5 — Project Closure (A161–A170)

Activity Summary Context Acceptance Criteria Other Information
A161 Validate deliverables/outcomes After A160; QA All deliverables validated; defects closed Quality checklist
A162 Formal acceptance After A161; sign-offs Stakeholder sign-offs recorded Audit trail
A163 Final testing & QA After A161; final suite No P1/P2 open; tests pass Security regression
A164 Final status & metrics After A162/A163; report Variance/EVM documented Benefits, schedule, cost
A165 Measure success vs KPIs After A164; verify KPI achievement verified Baselines/data lineage
A166 Validate business value/ROI After A165; finance ROI realized; CFO sign-off Sensitivity analysis
A167 Stakeholder satisfaction After A162; survey Results analyzed; actions logged Response rate target
A168 Lessons learned After A167; retrospective LL published with owners/dates Knowledge base entry
A169 Knowledge transfer to Ops After A164; KT Runbooks; on-call ready Hypercare period
A170 Handover & documentation After A169; closure Handover complete; access transferred Access reviews