ICT-Governance-Framework-Application

ICT Governance Framework - Schedule Development Input

Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Schedule Development Input
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025


Executive Summary

This document provides comprehensive inputs required for developing the ICT Governance Framework project schedule. It consolidates all necessary planning elements including activity lists, duration estimates, resource requirements, dependencies, constraints, and assumptions that enable the creation of a realistic, achievable project schedule supporting the $2.3M value delivery within the 15-month timeline.

Schedule Foundation: 180+ activities, 16,000 hours, 65-week duration Critical Inputs: 15 milestones, resource constraints, risk factors

Schedule Development Methodology

Schedule Development Approach

Schedule Development Tools

Schedule Validation Methods


ACTIVITY LIST INPUT

Activity Inventory Summary

Activity Categorization

  1. Critical Path Activities: Activities with zero float that determine project duration
  2. Near-Critical Activities: Activities with minimal float (1-5 days)
  3. Non-Critical Activities: Activities with significant float (>1 week)
  4. Milestone Activities: Zero-duration activities marking key achievements
  5. Summary Activities: Rolled-up activities representing work packages

Activity Attributes


DURATION ESTIMATES INPUT

Duration Estimation Summary

Phase Optimistic Most Likely Pessimistic Expected Duration
Initiation 15 days 20 days 30 days 21 days (4.2 weeks)
Analysis 32 days 40 days 55 days 41 days (8.2 weeks)
Development 85 days 100 days 130 days 103 days (20.6 weeks)
Deployment 32 days 40 days 55 days 41 days (8.2 weeks)
Closure 12 days 15 days 22 days 16 days (3.2 weeks)
TOTAL 176 days 215 days 292 days 222 days (44.4 weeks)

Duration Confidence Analysis

Duration Risk Factors

  1. Technical Complexity: Advanced integration and development requirements
  2. Resource Availability: Potential constraints on specialized resources
  3. External Dependencies: Third-party vendor and stakeholder availability
  4. Requirements Stability: Potential for scope changes during development
  5. Integration Challenges: Complexity of system integration activities

Duration Optimization Opportunities


RESOURCE REQUIREMENTS INPUT

Resource Category Summary

Resource Category Total Hours Peak Demand Constraint Level
Project Management 1,600 8 FTE Medium
Business Analysis 2,400 12 FTE High
Technical Development 5,600 28 FTE Critical
Architecture & Design 1,600 8 FTE High
Quality Assurance 1,600 10 FTE Medium
Data & Analytics 1,200 6 FTE High
Infrastructure/DevOps 800 5 FTE Medium
Change Management 800 4 FTE Low
Training & Support 800 6 FTE Low
External Consultants 1,000 Variable Critical

Resource Availability Constraints

  1. Senior Technical Architects: Limited to 2-3 resources organization-wide
  2. Governance Consultants: External resources with 6-8 week lead time
  3. Integration Specialists: Shared with other projects, 50% availability
  4. Security Experts: Limited internal capacity, requires external augmentation
  5. Change Management: Internal team supporting multiple initiatives

Resource Calendar Constraints

Resource Cost Inputs


DEPENDENCY RELATIONSHIPS INPUT

Internal Dependencies

Sequential Dependencies (Finish-to-Start)

Parallel Dependencies (Start-to-Start)

Finish-to-Finish Dependencies

External Dependencies

  1. Vendor Dependencies
    • Software license procurement (Lead time: 4-6 weeks)
    • Hardware delivery and installation (Lead time: 6-8 weeks)
    • Third-party system access and APIs (Lead time: 3-4 weeks)
  2. Stakeholder Dependencies
    • Executive approvals at phase gates (Duration: 3-5 days each)
    • User availability for requirements and testing (Variable availability)
    • IT infrastructure team support (Competing priorities)
  3. Organizational Dependencies
    • Budget approval cycles (Quarterly approval process)
    • Security review processes (2-3 week review cycles)
    • Change advisory board approvals (Weekly meeting cadence)

Dependency Risk Assessment


CONSTRAINTS INPUT

Schedule Constraints

  1. Fixed Deadline: Project must complete by end of Month 15 for budget reasons
  2. Phase Gate Constraints: Cannot proceed to next phase without gate approval
  3. Resource Constraints: Limited availability of specialized skills
  4. Budget Period Constraints: Expenditure must align with fiscal year budgets
  5. Compliance Constraints: Security reviews required before production deployment

Resource Constraints

  1. Internal Resources: Maximum 35 FTE available for project
  2. External Budget: $500K limit for external consultants and contractors
  3. Specialized Skills: Limited availability of governance and security experts
  4. Shared Resources: Some resources shared with other organizational priorities
  5. Geographic Constraints: Some resources only available in specific locations

Technical Constraints

  1. System Availability: Production systems have limited maintenance windows
  2. Integration Constraints: Must integrate with existing enterprise systems
  3. Security Constraints: All development must comply with security policies
  4. Performance Constraints: System must support 500+ concurrent users
  5. Compliance Constraints: Must meet regulatory requirements throughout development

Business Constraints

  1. Budget Constraints: Total project budget capped at $1.275M Year 1
  2. User Availability: Business users have limited time for project activities
  3. Change Management: Organization has limited change capacity
  4. Training Constraints: User training must fit within business schedules
  5. Go-Live Constraints: System launch must avoid peak business periods

ASSUMPTIONS INPUT

Schedule Assumptions

  1. Resource Availability: Planned resources will be available as scheduled
  2. Productivity Rates: Team productivity will meet industry standard benchmarks
  3. Learning Curve: Team will achieve full productivity within 2-4 weeks
  4. Requirements Stability: Requirements will remain stable after baselined
  5. Technology Performance: Selected technology will meet performance requirements

Resource Assumptions

  1. Skill Levels: Resources will possess required skill levels and certifications
  2. Team Dynamics: Project team will work effectively with minimal conflicts
  3. External Resources: Consultants and contractors will be available as needed
  4. Training Requirements: Minimal training required for team members
  5. Retention: Key team members will remain available throughout project

Technical Assumptions

  1. System Integration: Existing systems will support required integrations
  2. Performance Scalability: Architecture will scale to meet user load requirements
  3. Technology Stability: Selected technologies will remain stable and supported
  4. Data Quality: Existing data quality will support migration requirements
  5. Infrastructure Capacity: Current infrastructure can support new system

Business Assumptions

  1. Stakeholder Commitment: Stakeholders will remain committed throughout project
  2. User Adoption: Users will adopt new system with appropriate training
  3. Process Change: Business processes can be modified to leverage new capabilities
  4. Budget Stability: Project budget will remain stable throughout execution
  5. Organizational Priorities: Project will remain organizational priority

RISK FACTORS INPUT

Schedule Risk Categories

High Impact Risks (>4 weeks potential delay)

  1. Key Resource Loss: Departure of critical team members during project
  2. Requirements Creep: Significant scope expansion during development
  3. Technical Integration Issues: Major integration problems with existing systems
  4. External Vendor Delays: Critical vendor deliveries delayed beyond contingency
  5. Stakeholder Decision Delays: Extended delays in critical approval decisions

Medium Impact Risks (1-4 weeks potential delay)

  1. Resource Availability Issues: Planned resources unavailable when needed
  2. Technical Performance Problems: System performance below requirements
  3. Quality Issues: Significant defects requiring extensive rework
  4. Change Management Resistance: User resistance requiring additional effort
  5. Infrastructure Issues: Production infrastructure problems during deployment

Low Impact Risks (<1 week potential delay)

  1. Minor Requirement Changes: Small adjustments to requirements
  2. Team Learning Curve: Slower than expected team productivity ramp-up
  3. Communication Issues: Coordination problems between team members
  4. Documentation Delays: Delays in non-critical documentation activities
  5. Training Schedule Conflicts: Minor conflicts with user training schedules

Risk Response Strategies

Schedule Contingency Planning


MILESTONE INTEGRATION INPUT

Milestone Schedule Impact

  1. Phase Gates: Milestones serve as mandatory schedule checkpoints
  2. Decision Points: Milestone achievement enables subsequent activity authorization
  3. Resource Gates: Milestone completion triggers resource allocation for next phase
  4. Budget Gates: Budget release tied to milestone achievement validation
  5. Quality Gates: Quality validation required for milestone completion

Critical Milestones for Schedule

Milestone Buffer Management


WORK BREAKDOWN STRUCTURE INTEGRATION

WBS Schedule Mapping

Work Package Schedule Requirements

  1. Clear Start/End Points: Each work package has defined schedule boundaries
  2. Resource Assignment: Resources assigned at work package level
  3. Duration Estimates: Work package durations support phase planning
  4. Dependency Management: Inter-work package dependencies clearly defined
  5. Quality Criteria: Work package completion criteria support milestone achievement

Schedule Hierarchy Structure

Project Schedule
├── Phase 1: Project Initiation (4 weeks)
│   ├── WP 1.1: Project Foundation (2 weeks)
│   ├── WP 1.2: Stakeholder Engagement (2 weeks)
│   └── WP 1.3: Team Formation (3 weeks - parallel)
├── Phase 2: Analysis and Design (8 weeks)
│   ├── WP 2.1: Current State Assessment (4 weeks)
│   ├── WP 2.2: Requirements Analysis (3 weeks)
│   └── WP 2.3: Solution Architecture (4 weeks)
├── Phase 3: Development and Implementation (20 weeks)
│   ├── WP 3.1: Core Platform Development (15 weeks)
│   ├── WP 3.2: Integration Development (10 weeks)
│   └── WP 3.3: Quality Assurance (8 weeks)
├── Phase 4: Deployment and Rollout (8 weeks)
│   ├── WP 4.1: Infrastructure Preparation (3 weeks)
│   ├── WP 4.2: Pilot Program (4 weeks)
│   └── WP 4.3: Production Deployment (5 weeks)
└── Phase 5: Project Closure (3 weeks)
    ├── WP 5.1: Success Validation (2 weeks)
    └── WP 5.2: Knowledge Transfer (2 weeks)

CALENDAR AND WORKING TIME INPUT

Project Calendar Definition

Holiday and Exception Calendar

Resource Calendar Variations

Calendar Risk Factors


SCHEDULE DEVELOPMENT CONSTRAINTS

Methodology Constraints

  1. Critical Path Method Required: Must use CPM for schedule calculation
  2. Resource Leveling Required: Must balance resource allocation across timeline
  3. Monthly Reporting: Schedule must support monthly progress reporting cycles
  4. Milestone Tracking: Must track milestone achievement with variance analysis
  5. Baseline Management: Must maintain approved baseline for change control

Tool and System Constraints

  1. Enterprise Tools: Must use organization-standard project management tools
  2. Integration Requirements: Schedule must integrate with enterprise systems
  3. Reporting Standards: Must comply with organizational reporting standards
  4. Data Security: Schedule data must comply with data security requirements
  5. Version Control: Must maintain version control for schedule changes

Organizational Constraints

  1. Approval Processes: Schedule changes require formal approval processes
  2. Resource Management: Must coordinate with enterprise resource management
  3. Budget Integration: Schedule must align with budget management systems
  4. Stakeholder Reporting: Must provide schedule information in standard formats
  5. Archive Requirements: Must maintain schedule archives for historical reference

QUALITY ASSURANCE FOR SCHEDULE DEVELOPMENT

Schedule Quality Criteria

  1. Logical Consistency: All dependencies are logical and necessary
  2. Resource Feasibility: Resource assignments are realistic and achievable
  3. Duration Accuracy: Activity durations reflect realistic work estimates
  4. Critical Path Validity: Critical path represents actual project constraints
  5. Float Distribution: Float analysis provides meaningful schedule flexibility

Schedule Validation Process

  1. Technical Review: Validate schedule logic and calculations
  2. Resource Review: Confirm resource availability and assignments
  3. Stakeholder Review: Validate schedule with business stakeholders
  4. Risk Assessment: Evaluate schedule risks and mitigation strategies
  5. Approval Process: Obtain formal approval for schedule baseline

Schedule Review Checkpoints


CONTINUOUS IMPROVEMENT INPUT

Schedule Performance Metrics

  1. Schedule Performance Index (SPI): Measure schedule efficiency
  2. Critical Path Performance: Track critical path activity completion
  3. Milestone Achievement Rate: Percentage of milestones completed on time
  4. Float Consumption: Rate of float consumption on non-critical activities
  5. Forecast Accuracy: Accuracy of schedule forecasts and projections

Lessons Learned Integration

Schedule Optimization Opportunities

  1. Activity Sequencing: Optimize activity sequences for efficiency
  2. Resource Optimization: Balance resource utilization across activities
  3. Risk Management: Proactive risk management to prevent schedule delays
  4. Technology Utilization: Use technology to accelerate development activities
  5. Process Improvement: Streamline processes to reduce activity durations

Conclusion

This Schedule Development Input document provides comprehensive foundation information for creating a realistic, achievable project schedule for the ICT Governance Framework project. The inputs address all critical aspects of schedule development including activities, durations, resources, dependencies, constraints, and quality requirements.

Key Schedule Development Success Factors:

Schedule Development Readiness: With these comprehensive inputs, the project team is ready to develop a detailed project schedule that supports successful delivery of the $2.3M value proposition within the 15-month timeline. The schedule will provide the framework for project execution, monitoring, and control while maintaining flexibility for risk response and change management.


Document Control:


These schedule development inputs provide the comprehensive foundation for creating an effective project schedule that enables successful delivery of the ICT Governance Framework transformation.