ICT-Governance-Framework-Application

ICT Governance Framework - Schedule Network Diagram

Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Schedule Network Diagram
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025


Executive Summary

This document presents the Schedule Network Diagram for the ICT Governance Framework project, illustrating the logical relationships and dependencies between all project activities. The network diagram serves as the foundation for project scheduling, critical path analysis, and resource optimization, supporting the successful delivery of the $2.3M value proposition within the 15-month timeline.

Project Duration: 65 weeks (15 months) Critical Path Duration: 63 weeks Total Activities: 180+ Major Milestones: 15

Network Diagram Methodology

Diagramming Approach

Diagram Components

Network Analysis Techniques


Project Phase Network Overview

High-Level Phase Dependencies

[Project Initiation] 
    ↓ FS
[Analysis & Design] 
    ↓ FS
[Development & Implementation] 
    ↓ FS
[Deployment & Rollout] 
    ↓ FS
[Project Closure]

Phase Interface Points


PHASE 1: PROJECT INITIATION - Network Details

Foundation Activity Network

[Project Start]
    ↓
[Define Project Scope (A001)] (3d)
    ↓ FS
[Develop Business Case (A002)] (5d)
    ↓ FS
[Identify Key Stakeholders (A003)] (2d)
    ↓ FS
[Define Success Criteria (A004)] (3d)
    ↓ FS
[Analyze Strategic Objectives (A005)] (5d)
    ↓ FS
[Map Governance Requirements (A006)] (4d)
    ↓ FS
[Identify Compliance Requirements (A007)] (6d)
    ↓ FS
[Validate Strategic Fit (A008)] (2d)
    ↓
[Foundation Complete - Milestone M1]

Stakeholder Engagement Network

[Foundation Complete] 
    ↓ FS (Start after foundation activities)
[Identify Stakeholders (A009)] (2d)
    ↓ FS
[Analyze Stakeholder Influence (A010)] (2d) ←---
    ↓ FS                                        |
[Develop Engagement Strategies (A011)] (4d)     | SS+1d
    ↓ FS                                        |
[Create Stakeholder Register (A012)] (3d) ------
    ↓ FS
[Establish Communication Channels (A013)] (2d)
    ↓ FS 
[Setup Collaboration Platforms (A014)] (3d)
    ↓ FS
[Create Communication Templates (A015)] (2d) 
    ↓ FS
[Implement Feedback Mechanisms (A016)] (2d)
    ↓
[Stakeholder Engagement Complete - Milestone M2]

Team Formation Network (Parallel Path)

[Project Start]
    ↓ SS+5d (Start 5 days after project start)
[Recruit Core Team (A017)] (5d)
    ↓ FS
[Define Roles and Responsibilities (A018)] (3d)
    ↓ FS
[Establish Working Agreements (A019)] (2d) 
    ↓ FS
[Conduct Team Orientation (A020)] (3d)
    ↓
[Team Formation Complete]

Phase 1 Integration Network

[Stakeholder Engagement Complete] 
    ↓ FS
[Team Formation Complete] 
    ↓ FS
[Project Charter Creation (A004)] (3d)
    ↓ FS
[Charter Approval Process] (2d)
    ↓
[Phase 1 Gate Review] (1d)
    ↓
[Phase 1 Complete - Milestone M3]

Phase 1 Critical Path: A001→A002→A003→A004→A005→A006→A007→A008→M1→A009→A010→A011→A012→A013→A014→A015→A016→M2→Charter→Approval→M3 Phase 1 Duration: 20 work days (4 weeks)


PHASE 2: ANALYSIS & DESIGN - Network Details

Current State Assessment Network

[Phase 1 Complete]
    ↓ FS
[Evaluate Current Practices (A021)] (10d)
    ↓ FS
[Assess Governance Maturity (A022)] (8d) ←-----
    ↓ FS                                      |
[Identify Governance Gaps (A023)] (8d)        | SS+2d
    ↓ FS                                      |
[Document Current Architecture (A024)] (5d) ---|
    ↓ FS
[Inventory Technology Assets (A025)] (6d)
    ↓ FS
[Assess IT Architecture (A026)] (8d)
    ↓ FS
[Evaluate Integration Requirements (A027)] (6d)
    ↓ FS
[Analyze Performance (A028)] (4d)
    ↓
[Current State Complete - Milestone M4]

Requirements Analysis Network

[Current State Complete]
    ↓ FS
[Gather Stakeholder Requirements (A029)] (12d)
    ↓ FS
[Define Functional Requirements (A030)] (10d) ←---
    ↓ FS                                          |
[Prioritize Requirements (A031)] (6d)             | SS+5d
    ↓ FS                                          |
[Create Requirements Documentation (A032)] (8d) ---|
    ↓ FS
[Identify Regulatory Frameworks (A033)] (6d)
    ↓ FS
[Map Compliance Features (A034)] (8d)
    ↓
[Requirements Complete - Milestone M5]

Solution Architecture Network

[Requirements Complete]
    ↓ FS
[Design Operating Model (A035)] (12d)
    ↓ FS
[Define Processes (A036)] (15d) ←--------
    ↓ FS                                |
[Create Roles Matrix (A037)] (8d)       | SS+3d
    ↓ FS                                |
[Develop Policies (A038)] (10d) --------|
    ↓ FS
[Design System Architecture (A039)] (12d)
    ↓ FS
[Define Data Model (A040)] (8d)
    ↓
[Architecture Complete - Milestone M6]

Phase 2 Integration and Approval

[Architecture Complete]
    ↓ FS
[Requirements Review Session] (2d)
    ↓ FS
[Architecture Review Board] (1d)
    ↓ FS
[Stakeholder Approval Process] (3d)
    ↓ FS
[Phase 2 Gate Review] (2d)
    ↓
[Phase 2 Complete - Milestone M7]

Phase 2 Critical Path: M3→A021→A022→A023→M4→A029→A030→A031→A032→M5→A035→A036→A037→A038→A039→A040→M6→Reviews→M7 Phase 2 Duration: 40 work days (8 weeks)


PHASE 3: DEVELOPMENT & IMPLEMENTATION - Network Details

Core Platform Development Network (Critical Path)

[Phase 2 Complete]
    ↓ FS
[Setup Development Environment (A041)] (3d)
    ↓ FS
[Develop Workflow Engine (A061)] (30d)
    ↓ FS
[Implement User Management (A062)] (20d)
    ↓ FS
[Create Document Management (A063)] (18d)
    ↓ FS
[Build Communication Features (A064)] (15d)
    ↓ FS
[Develop Data Processing (A065)] (20d)
    ↓ FS
[Core Platform Complete - Milestone M8]

Analytics and Reporting Network (Parallel Path)

[Setup Development Environment]
    ↓ SS+10d
[Implement Dashboard (A066)] (18d)
    ↓ FS
[Create Reporting Functions (A067)] (12d)
    ↓ FS
[Build Analytics Engine (A068)] (15d)
    ↓
[Analytics Complete]

Integration Development Network (Parallel Path)

[Core Platform 50% Complete]
    ↓ FS
[Develop API Framework (A069)] (20d)
    ↓ FS
[Implement System Connectors (A070)] (18d) ←---
    ↓ FS                                       |
[Create Data Synchronization (A071)] (12d)     | SS+5d
    ↓ FS                                       |
[Build Monitoring (A072)] (10d) --------------|
    ↓
[Integration Complete]

Quality Assurance Network (Integrated)

[Core Platform Complete]
    ↓ FS
[Develop Testing Strategy (A073)] (4d)
    ↓ FS
[Create Test Cases (A074)] (8d) ←-----------
    ↓ FS                                   |
[Execute Unit Testing (A075)] (12d)        | SS+2d
    ↓ FS                                   |
[System Testing (A076)] (15d) -------------|
    ↓ FS
[User Acceptance Testing (A077)] (12d)
    ↓ FS
[Performance Testing (A078)] (8d)
    ↓
[Quality Assurance Complete - Milestone M9]

Phase 3 Integration Point

[Core Platform Complete]
    ↓ FS
[Analytics Complete]
    ↓ FS
[Integration Complete]
    ↓ FS
[Quality Assurance Complete]
    ↓ FS
[System Integration Testing] (10d)
    ↓ FS
[Final System Validation] (5d)
    ↓ FS
[Phase 3 Gate Review] (2d)
    ↓
[Phase 3 Complete - Milestone M10]

Phase 3 Critical Path: M7→A041→A061→A062→A063→A064→A065→M8→A073→A074→A075→A076→A077→A078→M9→Integration→Validation→M10 Phase 3 Duration: 100 work days (20 weeks)


PHASE 4: DEPLOYMENT & ROLLOUT - Network Details

Infrastructure Preparation Network

[Phase 3 Complete]
    ↓ FS
[Provision Infrastructure (A121)] (8d)
    ↓ FS
[Install Software (A122)] (6d) ←--------
    ↓ FS                               |
[Implement Security (A123)] (5d)       | SS+2d
    ↓ FS                               |
[Infrastructure Testing (A124)] (4d) ---|
    ↓
[Infrastructure Ready - Milestone M11]

Data Migration Network (Parallel Path)

[Phase 3 Complete]
    ↓ SS+5d
[Prepare Migration (A125)] (6d)
    ↓ FS
[Execute Migration (A126)] (8d)
    ↓ FS
[Validate Data (A127)] (4d)
    ↓
[Data Migration Complete]

Pilot Program Network

[Infrastructure Ready]
    ↓ FS
[Data Migration Complete]
    ↓ FS
[Plan Pilot (A128)] (5d)
    ↓ FS
[Execute Pilot (A129)] (8d)
    ↓ FS
[Analyze Results (A130)] (4d)
    ↓
[Pilot Complete - Milestone M12]

Production Deployment Network

[Pilot Complete]
    ↓ FS
[Production Deployment (A131)] (3d)
    ↓ FS
[User Training (A132)] (12d) ←---------
    ↓ FS                              |
[Go-Live Support (A133)] (8d)         | SS+5d
    ↓                                 |
[Production Monitoring] (5d) ---------|
    ↓
[Deployment Complete - Milestone M13]

Phase 4 Integration

[Deployment Complete]
    ↓ FS
[User Feedback Collection] (3d)
    ↓ FS
[System Performance Validation] (2d)
    ↓ FS
[Phase 4 Gate Review] (2d)
    ↓
[Phase 4 Complete - Milestone M14]

Phase 4 Critical Path: M10→A121→A122→A123→A124→M11→A125→A126→A127→A128→A129→A130→M12→A131→A132→A133→M13→M14 Phase 4 Duration: 40 work days (8 weeks)


PHASE 5: PROJECT CLOSURE - Network Details

Project Completion Network

[Phase 4 Complete]
    ↓ FS
[Validate Deliverables (A161)] (4d)
    ↓ FS
[Obtain Acceptance (A162)] (3d)
    ↓ FS
[Final Testing (A163)] (4d)
    ↓ FS
[Document Status (A164)] (2d)
    ↓
[Completion Validated]

Success Validation Network (Parallel Path)

[Phase 4 Complete]
    ↓ SS+2d
[Measure Success (A165)] (4d) ←--------
    ↓ FS                              |
[Validate ROI (A166)] (3d)             | SS+1d
    ↓ FS                              |
[Assess Satisfaction (A167)] (3d) -----|
    ↓ FS
[Document Lessons (A168)] (2d)
    ↓
[Success Validated]

Knowledge Transfer Network

[Completion Validated]
    ↓ FS
[Success Validated]
    ↓ FS
[Transfer Knowledge (A169)] (5d)
    ↓ FS
[Conduct Handover (A170)] (4d)
    ↓
[Knowledge Transfer Complete]

Project Closure Integration

[Knowledge Transfer Complete]
    ↓ FS
[Final Project Report] (2d)
    ↓ FS
[Stakeholder Sign-off] (1d)
    ↓ FS
[Project Archive] (1d)
    ↓
[Project Complete - Milestone M15]

Phase 5 Critical Path: M14→A161→A162→A163→A164→A165→A166→A167→A168→A169→A170→Report→Sign-off→M15 Phase 5 Duration: 15 work days (3 weeks)


Critical Path Analysis

Overall Project Critical Path

[Project Start] → [Foundation Activities] → [Current State Assessment] → 
[Requirements Analysis] → [Solution Architecture] → [Core Development] → 
[Quality Assurance] → [Infrastructure Preparation] → [Pilot Program] → 
[Production Deployment] → [Project Closure] → [Project Complete]

Critical Path Activities (63 weeks)

  1. Foundation Phase (4 weeks): Project scope → Business case → Stakeholder analysis → Charter approval
  2. Analysis Phase (8 weeks): Current state assessment → Requirements gathering → Architecture design
  3. Development Phase (20 weeks): Core platform development → QA testing → System validation
  4. Deployment Phase (8 weeks): Infrastructure setup → Pilot program → Production deployment
  5. Closure Phase (3 weeks): Success validation → Knowledge transfer → Project completion

Float Analysis


Schedule Optimization Opportunities

Fast-Tracking Opportunities

  1. Parallel Development Streams: Run analytics and integration development in parallel (Save 5 weeks)
  2. Overlapping Phases: Begin infrastructure preparation during final development (Save 3 weeks)
  3. Concurrent Testing: Execute system and integration testing simultaneously (Save 2 weeks)
  4. Pre-deployment Activities: Start user training during pilot phase (Save 1 week)

Resource Optimization

  1. Critical Resource Focus: Prioritize best resources on critical path activities
  2. Resource Leveling: Balance resource allocation across parallel activities
  3. Cross-Training: Train team members on multiple skills to provide flexibility
  4. External Resources: Use contractors for non-critical path activities

Schedule Compression Techniques


Risk Impact on Network Schedule

Schedule Risk Factors

  1. Resource Availability: Key resource unavailability could delay critical path (Risk: 2-4 weeks)
  2. Technical Complexity: Underestimated complexity in core development (Risk: 3-6 weeks)
  3. Integration Challenges: System integration issues (Risk: 2-5 weeks)
  4. Stakeholder Decisions: Delayed approvals and decisions (Risk: 1-3 weeks)
  5. External Dependencies: Third-party system availability (Risk: 1-4 weeks)

Risk Mitigation in Network

Contingency Network Paths

  1. Accelerated Development: Parallel development streams to recover lost time
  2. Phased Deployment: Split deployment into phases to accelerate delivery
  3. Minimum Viable Product: Deliver core functionality first, enhance later
  4. Resource Surge: Add resources temporarily to critical activities

Network Diagram Quality Assurance

Diagram Validation Criteria

Dependency Validation

  1. Mandatory Dependencies: Hard logic based on technical or physical requirements
  2. Discretionary Dependencies: Soft logic based on best practices or preferences
  3. External Dependencies: Dependencies on activities outside project control
  4. Resource Dependencies: Activities that require the same limited resources

Network Review Process


Schedule Monitoring and Control

Network-Based Monitoring

Schedule Control Techniques

  1. Earned Value Management: Track schedule performance using earned value metrics
  2. Critical Chain Method: Focus on resource constraints and buffer management
  3. Agile Techniques: Use iterative development within network constraints
  4. Rolling Wave Planning: Detailed planning for near-term activities

Schedule Update Process


Integration with Other Planning Documents

Activity List Integration

Work Breakdown Structure Integration

Risk Management Integration


Conclusion

The Schedule Network Diagram provides a comprehensive foundation for project scheduling, resource planning, and schedule management. With a critical path duration of 63 weeks and strategic optimization opportunities, the network enables efficient project execution while maintaining flexibility for risk response and change management.

Key Network Characteristics:

The network diagram supports successful delivery of the ICT Governance Framework within the 15-month timeline while enabling proactive schedule management and optimization throughout project execution.


Document Control:


This Schedule Network Diagram provides the logical foundation for project scheduling, enabling effective time management and successful delivery of the ICT Governance Framework transformation.