Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Schedule Network Diagram
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025
This document presents the Schedule Network Diagram for the ICT Governance Framework project, illustrating the logical relationships and dependencies between all project activities. The network diagram serves as the foundation for project scheduling, critical path analysis, and resource optimization, supporting the successful delivery of the $2.3M value proposition within the 15-month timeline.
Project Duration: 65 weeks (15 months) | Critical Path Duration: 63 weeks | Total Activities: 180+ | Major Milestones: 15 |
[Project Initiation]
↓ FS
[Analysis & Design]
↓ FS
[Development & Implementation]
↓ FS
[Deployment & Rollout]
↓ FS
[Project Closure]
[Project Start]
↓
[Define Project Scope (A001)] (3d)
↓ FS
[Develop Business Case (A002)] (5d)
↓ FS
[Identify Key Stakeholders (A003)] (2d)
↓ FS
[Define Success Criteria (A004)] (3d)
↓ FS
[Analyze Strategic Objectives (A005)] (5d)
↓ FS
[Map Governance Requirements (A006)] (4d)
↓ FS
[Identify Compliance Requirements (A007)] (6d)
↓ FS
[Validate Strategic Fit (A008)] (2d)
↓
[Foundation Complete - Milestone M1]
[Foundation Complete]
↓ FS (Start after foundation activities)
[Identify Stakeholders (A009)] (2d)
↓ FS
[Analyze Stakeholder Influence (A010)] (2d) ←---
↓ FS |
[Develop Engagement Strategies (A011)] (4d) | SS+1d
↓ FS |
[Create Stakeholder Register (A012)] (3d) ------
↓ FS
[Establish Communication Channels (A013)] (2d)
↓ FS
[Setup Collaboration Platforms (A014)] (3d)
↓ FS
[Create Communication Templates (A015)] (2d)
↓ FS
[Implement Feedback Mechanisms (A016)] (2d)
↓
[Stakeholder Engagement Complete - Milestone M2]
[Project Start]
↓ SS+5d (Start 5 days after project start)
[Recruit Core Team (A017)] (5d)
↓ FS
[Define Roles and Responsibilities (A018)] (3d)
↓ FS
[Establish Working Agreements (A019)] (2d)
↓ FS
[Conduct Team Orientation (A020)] (3d)
↓
[Team Formation Complete]
[Stakeholder Engagement Complete]
↓ FS
[Team Formation Complete]
↓ FS
[Project Charter Creation (A004)] (3d)
↓ FS
[Charter Approval Process] (2d)
↓
[Phase 1 Gate Review] (1d)
↓
[Phase 1 Complete - Milestone M3]
Phase 1 Critical Path: A001→A002→A003→A004→A005→A006→A007→A008→M1→A009→A010→A011→A012→A013→A014→A015→A016→M2→Charter→Approval→M3 Phase 1 Duration: 20 work days (4 weeks)
[Phase 1 Complete]
↓ FS
[Evaluate Current Practices (A021)] (10d)
↓ FS
[Assess Governance Maturity (A022)] (8d) ←-----
↓ FS |
[Identify Governance Gaps (A023)] (8d) | SS+2d
↓ FS |
[Document Current Architecture (A024)] (5d) ---|
↓ FS
[Inventory Technology Assets (A025)] (6d)
↓ FS
[Assess IT Architecture (A026)] (8d)
↓ FS
[Evaluate Integration Requirements (A027)] (6d)
↓ FS
[Analyze Performance (A028)] (4d)
↓
[Current State Complete - Milestone M4]
[Current State Complete]
↓ FS
[Gather Stakeholder Requirements (A029)] (12d)
↓ FS
[Define Functional Requirements (A030)] (10d) ←---
↓ FS |
[Prioritize Requirements (A031)] (6d) | SS+5d
↓ FS |
[Create Requirements Documentation (A032)] (8d) ---|
↓ FS
[Identify Regulatory Frameworks (A033)] (6d)
↓ FS
[Map Compliance Features (A034)] (8d)
↓
[Requirements Complete - Milestone M5]
[Requirements Complete]
↓ FS
[Design Operating Model (A035)] (12d)
↓ FS
[Define Processes (A036)] (15d) ←--------
↓ FS |
[Create Roles Matrix (A037)] (8d) | SS+3d
↓ FS |
[Develop Policies (A038)] (10d) --------|
↓ FS
[Design System Architecture (A039)] (12d)
↓ FS
[Define Data Model (A040)] (8d)
↓
[Architecture Complete - Milestone M6]
[Architecture Complete]
↓ FS
[Requirements Review Session] (2d)
↓ FS
[Architecture Review Board] (1d)
↓ FS
[Stakeholder Approval Process] (3d)
↓ FS
[Phase 2 Gate Review] (2d)
↓
[Phase 2 Complete - Milestone M7]
Phase 2 Critical Path: M3→A021→A022→A023→M4→A029→A030→A031→A032→M5→A035→A036→A037→A038→A039→A040→M6→Reviews→M7 Phase 2 Duration: 40 work days (8 weeks)
[Phase 2 Complete]
↓ FS
[Setup Development Environment (A041)] (3d)
↓ FS
[Develop Workflow Engine (A061)] (30d)
↓ FS
[Implement User Management (A062)] (20d)
↓ FS
[Create Document Management (A063)] (18d)
↓ FS
[Build Communication Features (A064)] (15d)
↓ FS
[Develop Data Processing (A065)] (20d)
↓ FS
[Core Platform Complete - Milestone M8]
[Setup Development Environment]
↓ SS+10d
[Implement Dashboard (A066)] (18d)
↓ FS
[Create Reporting Functions (A067)] (12d)
↓ FS
[Build Analytics Engine (A068)] (15d)
↓
[Analytics Complete]
[Core Platform 50% Complete]
↓ FS
[Develop API Framework (A069)] (20d)
↓ FS
[Implement System Connectors (A070)] (18d) ←---
↓ FS |
[Create Data Synchronization (A071)] (12d) | SS+5d
↓ FS |
[Build Monitoring (A072)] (10d) --------------|
↓
[Integration Complete]
[Core Platform Complete]
↓ FS
[Develop Testing Strategy (A073)] (4d)
↓ FS
[Create Test Cases (A074)] (8d) ←-----------
↓ FS |
[Execute Unit Testing (A075)] (12d) | SS+2d
↓ FS |
[System Testing (A076)] (15d) -------------|
↓ FS
[User Acceptance Testing (A077)] (12d)
↓ FS
[Performance Testing (A078)] (8d)
↓
[Quality Assurance Complete - Milestone M9]
[Core Platform Complete]
↓ FS
[Analytics Complete]
↓ FS
[Integration Complete]
↓ FS
[Quality Assurance Complete]
↓ FS
[System Integration Testing] (10d)
↓ FS
[Final System Validation] (5d)
↓ FS
[Phase 3 Gate Review] (2d)
↓
[Phase 3 Complete - Milestone M10]
Phase 3 Critical Path: M7→A041→A061→A062→A063→A064→A065→M8→A073→A074→A075→A076→A077→A078→M9→Integration→Validation→M10 Phase 3 Duration: 100 work days (20 weeks)
[Phase 3 Complete]
↓ FS
[Provision Infrastructure (A121)] (8d)
↓ FS
[Install Software (A122)] (6d) ←--------
↓ FS |
[Implement Security (A123)] (5d) | SS+2d
↓ FS |
[Infrastructure Testing (A124)] (4d) ---|
↓
[Infrastructure Ready - Milestone M11]
[Phase 3 Complete]
↓ SS+5d
[Prepare Migration (A125)] (6d)
↓ FS
[Execute Migration (A126)] (8d)
↓ FS
[Validate Data (A127)] (4d)
↓
[Data Migration Complete]
[Infrastructure Ready]
↓ FS
[Data Migration Complete]
↓ FS
[Plan Pilot (A128)] (5d)
↓ FS
[Execute Pilot (A129)] (8d)
↓ FS
[Analyze Results (A130)] (4d)
↓
[Pilot Complete - Milestone M12]
[Pilot Complete]
↓ FS
[Production Deployment (A131)] (3d)
↓ FS
[User Training (A132)] (12d) ←---------
↓ FS |
[Go-Live Support (A133)] (8d) | SS+5d
↓ |
[Production Monitoring] (5d) ---------|
↓
[Deployment Complete - Milestone M13]
[Deployment Complete]
↓ FS
[User Feedback Collection] (3d)
↓ FS
[System Performance Validation] (2d)
↓ FS
[Phase 4 Gate Review] (2d)
↓
[Phase 4 Complete - Milestone M14]
Phase 4 Critical Path: M10→A121→A122→A123→A124→M11→A125→A126→A127→A128→A129→A130→M12→A131→A132→A133→M13→M14 Phase 4 Duration: 40 work days (8 weeks)
[Phase 4 Complete]
↓ FS
[Validate Deliverables (A161)] (4d)
↓ FS
[Obtain Acceptance (A162)] (3d)
↓ FS
[Final Testing (A163)] (4d)
↓ FS
[Document Status (A164)] (2d)
↓
[Completion Validated]
[Phase 4 Complete]
↓ SS+2d
[Measure Success (A165)] (4d) ←--------
↓ FS |
[Validate ROI (A166)] (3d) | SS+1d
↓ FS |
[Assess Satisfaction (A167)] (3d) -----|
↓ FS
[Document Lessons (A168)] (2d)
↓
[Success Validated]
[Completion Validated]
↓ FS
[Success Validated]
↓ FS
[Transfer Knowledge (A169)] (5d)
↓ FS
[Conduct Handover (A170)] (4d)
↓
[Knowledge Transfer Complete]
[Knowledge Transfer Complete]
↓ FS
[Final Project Report] (2d)
↓ FS
[Stakeholder Sign-off] (1d)
↓ FS
[Project Archive] (1d)
↓
[Project Complete - Milestone M15]
Phase 5 Critical Path: M14→A161→A162→A163→A164→A165→A166→A167→A168→A169→A170→Report→Sign-off→M15 Phase 5 Duration: 15 work days (3 weeks)
[Project Start] → [Foundation Activities] → [Current State Assessment] →
[Requirements Analysis] → [Solution Architecture] → [Core Development] →
[Quality Assurance] → [Infrastructure Preparation] → [Pilot Program] →
[Production Deployment] → [Project Closure] → [Project Complete]
The Schedule Network Diagram provides a comprehensive foundation for project scheduling, resource planning, and schedule management. With a critical path duration of 63 weeks and strategic optimization opportunities, the network enables efficient project execution while maintaining flexibility for risk response and change management.
Key Network Characteristics:
The network diagram supports successful delivery of the ICT Governance Framework within the 15-month timeline while enabling proactive schedule management and optimization throughout project execution.
Document Control:
This Schedule Network Diagram provides the logical foundation for project scheduling, enabling effective time management and successful delivery of the ICT Governance Framework transformation.