ICT Governance Framework - Work Breakdown Structure (WBS)

Project: ICT Governance Framework Application
Document Type: Planning Artifacts - Work Breakdown Structure
Version: 1.0
Prepared by: ICT Governance Project Team
Date: August 8, 2025


Executive Summary

This Work Breakdown Structure (WBS) provides a comprehensive hierarchical decomposition of the ICT Governance Framework project deliverables and work components. The WBS serves as the foundation for project planning, resource allocation, cost estimation, and progress tracking.

Project Investment: $1.275M Year 1 Expected Value: $2.3M Annual Project Duration: 15 months

WBS Structure Overview

The ICT Governance Framework WBS is organized into 5 major phases with multiple work packages and activities. Each element is uniquely identified with a WBS code for easy reference and tracking.

WBS Numbering Convention


🏗️ 1.0 ICT Governance Framework Project

1.1 Project Initiation Phase

Duration: 4 weeks | Budget: $95,000

1.1.1 Project Charter and Foundation

1.1.2 Stakeholder Engagement and Communication

1.1.3 Project Team Formation and Setup

1.1.4 Initial Risk and Quality Planning


1.2 Analysis and Design Phase

Duration: 8 weeks | Budget: $255,000

1.2.1 Current State Assessment

1.2.2 Requirements Analysis and Documentation

1.2.3 Solution Architecture and Design

1.2.4 User Experience and Interface Design


1.3 Development and Implementation Phase

Duration: 20 weeks | Budget: $510,000

1.3.1 Platform Development

1.3.2 Integration and Connectivity

1.3.3 Quality Assurance and Testing

1.3.4 Documentation and Training Materials


1.4 Deployment and Rollout Phase

Duration: 8 weeks | Budget: $255,000

1.4.1 Infrastructure Preparation and Setup

1.4.2 Pilot Implementation

1.4.3 Production Deployment

1.4.4 Go-Live Support and Stabilization


1.5 Project Closure and Transition Phase

Duration: 3 weeks | Budget: $160,000

1.5.1 Project Completion and Validation

1.5.2 Knowledge Transfer and Documentation

1.5.3 Resource Transition and Team Dissolution

1.5.4 Business Value Realization Planning


Cross-Cutting Work Packages

1.6 Project Management and Governance

Duration: 15 months (parallel) | Budget: Allocated across phases

1.6.1 Project Management Activities

1.6.2 Risk and Issue Management

1.6.3 Quality Assurance and Control

1.6.4 Change Management


WBS Summary Statistics

Project Totals

Phase Distribution

| Phase | Duration | Budget | % of Total | |——-|———-|———|————| | Initiation | 4 weeks | $95,000 | 7.5% | | Analysis & Design | 8 weeks | $255,000 | 20.0% | | Development & Implementation | 20 weeks | $510,000 | 40.0% | | Deployment & Rollout | 8 weeks | $255,000 | 20.0% | | Closure & Transition | 3 weeks | $160,000 | 12.5% |

Resource Allocation Summary


WBS Usage Guidelines

Planning and Estimation

Progress Tracking and Control

Resource Management

Risk and Issue Management


Integration with Project Management

Dependencies and Relationships

Critical Success Factors

Value Realization Alignment


Conclusion

This Work Breakdown Structure provides a comprehensive framework for managing the ICT Governance Framework project, ensuring systematic delivery of all project objectives while maintaining clear accountability and control. The hierarchical structure enables effective planning, resource allocation, progress tracking, and successful achievement of the $2.3M annual value proposition.

The WBS serves as the foundation for all project planning and control activities, ensuring systematic and successful delivery of the ICT Governance Framework transformation initiative.


Document Control:


This Work Breakdown Structure ensures systematic decomposition and management of all ICT Governance Framework project deliverables, supporting successful achievement of project objectives and value realization.